|
Subsurface Work Can Benefit From Some Small
Changes
By William J. Angelo
 |
 |
|
Brierley
|
While design-build
offers many well-known cost and savings advantages on building
and heavy civil projects, its use on subsurface projects such
as tunnels and deep foundations has been slow to catch on.
But that is changing. One way design-builders can help accelerate
the process is by adopting lessons learned from a long history
of successful design-bid-build projects.
When design-build goes underground,
the designer becomes liable for lots of risk not found on
a surface project, says Gary Brierley, president of Brierley
Associates, Littleton, Colo. "When you win [an underground]
design-build job, its equivalent to winning a foot race
over a cliff. Sometimes you survive, sometimes you dont."
Design-build can save time and
money underground but problems can arise if the designer and
constructor differ in their interpretation of the plans and
specifications or there are differing site conditions or surprise
environmental issues. The lesson that can be learned from
successful design-bid-build projects is that there must always
be clear communications among the parties and a fair and clear
assignment of risk, according to Brierley.
About 95% of Brierley Associates
work is underground design. The firm averages about $2.5 million
in annual revenue and has completed 12 design-build jobs.
Brierley believes that risk is increased when the contractor
uses one team to develop a proposal and win the project and
another team to build it. He says communications between the
two teams and the designer easily can break down and cause
friction. Frequently, the construction team feels that the
proposal team and the designer made too many concessions and
promises to the owner, he adds. "After the award, what
you typically get is a cost-driven project manager who just
wants to get the job done," says Brierley. "That
causes tension because the engineer, who is part of a team,
has no independent source of authority to get its way or to
accomplish significant design requirements and that may impact
long-term project performance."
Many important decisions must be
made without direct access to the owner. "The best way
to get the job done is to get all the correct answers from
the owner or to have it make the decisions before the project
is awarded," says Brierley. "But with design-build,
designers have to go through the contractor who may disagree
with their ideas, so where do the designers go if the owner
is out of the loop? Take one decision and multiply it by 100
or 300 times over the duration of the project and you could
have serious problems."
The designer sometimes becomes
the tail trying to wag the dog because it is very difficult
for the designer to obtain the authority to force an issue
with the contractor. A typical tunnel design might take three
months but the contractor wants it in six weeks and the designer
ends up doing it in two months. "Is that a one month
savings or two weeks delay? It all depends on how hard the
contractor wants to be," says Brierley.
To meet cost and schedule constraints,
some contractors may cut corners. Above- ground problems can
be fixed, below- ground problems can be a disaster. Many underground
projects have a service life of 75 to 100 years and are very
difficult and expensive to fix if problems arise after completion,
says Brierley. "When something goes wrong on a design-build
job its very easy to blame the designer," he says. "The
owner is insulated from risks and it is easy for the contractor
to say he relied on the professional judgement of the designer."
Many owners try to transfer all
ground-condition risks to the design-builder and many contractors
will hold the designer responsible if something goes wrong.
The designer therefore is greatly affected by the prime agreement,
says Brierley. Disputes can get expensive because underground
work can have a big impact on adjacent property, he adds.
Despite the concerns, there are
advantages to adopting some simple design-bid-build lessons.
"It all revolves around proper structure and behavior,"
says Brierley. "The owner still needs to do a thorough
subsurface investigation and the contract should include a
differing site conditions clause like you would find in a
typical design-bid-build contract. That may seem to contradict
design-build principals but it ensures reaching the owners
objective," says Brierley.
Designers also need the kind of
authority they have in traditional project delivery, says
Brierley. "The owner must ensure that the designer has
full authority to implement a safe finished facility....This
must be addressed in the prime agreement, like you would find
in a D-B-B deal," he says. "Its OK to be cost
effective on temporary facilities and means and methods, but
the important design characteristics of the finished facility
must be right."
Owners should be made aware of
the consequences of passing off critical decisions to the
design-build team. But properly done, design-build can offer
significant advantages on subsurface work.
|