|
Ecuador Building New Capitol City Airport
With design about one-third complete, construction is about
to start on a new $400-million airport for the Ecuadorian
capital, Quito. Sited where future expansion is possible,
some 18-kilometer east of the city, the new facility will
replace the overtaxed existing airport.
Air traffic is expected to grow 4.5 to 5.5% a year and the
planned 3.6-kilometer runway will be expanded to 4.1 km before
a second runway is added. The 38,000-sq-m terminal is planned
initially for up to 4 million passengers per year. Passenger
throughput is due to reach about 7.5 million in a second phase,
when needed. The airport "is designed for maximum flexibility
to allow international and domestic growth," according
to Massimo Polveraccio, director of infrastructure private
finance at Aecon Construction Group Inc., Toronto.
Aecon and Brazils Andrade Gutierrez Concessões
S.A., Saõ Paulo, equally share nearly 70% of Corporación
Quiport S.A., which has a fixed-price, lump-sum, date-certain
design-build contract with Canadian Commercial Corp. The company
is developing the airport under a 35-year intergovernmental
agreement between Ecuador and Canada.
Construction must be completed within 51 months, says Polveraccio.
"A large component of the construction contract will
be subcontracted locally to various companies," he adds.
Design is by API Architects Inc., with engineering by Marshall
Macklin Monahan Ltd., both of Toronto.

Wastewater Treatment Attracts Earth Tech to Mexico
By combining design-build with operations (DBO) and sometimes
also with financing (DBFO), Long Beach, California-based Earth
Tech Inc. has built a steady business in delivering long-needed
Mexican wastewater treatment facilities. Its most recent DBFO
project in Chihuahua is due for completion in January 2006.
The 50-mgd plant, which will raise capacity 100% for treating
the citys non-agricultural wastewater, carries a 10-year
operations deal. Earth Tech also had built the citys
existing 25-mgd plant, which the firm has been operating for
the past nine years.
Under another DBFO deal, Earth Tech is building a $22-million
municipal wastewater treatment plant at Xalapa, and is operating
four industrial units for the state oil company. Early last
year, Earth Tech began operating a 28-mgd plant in Veracruz
under a 15-year DBO contract. A few months later it won another,
$22.5-million DBO award for four plants (Mexicali, Guadalupe
Victoria, Estacion Coahuila and Los Algodones) in Mexicali,
Baja California. Including expansion of two other units (Mexicali
and Ciudad Morelos), the six plants combined will handle 50
mgd starting in late 2006.

Chile Builds Suspense Into Suspension Bridge
 |
 |
|
A three-tower, 2,635-meter-long suspension bridge could tame Chile’s Chacao Channel.
|
Winning a $625-million contract for the design and construction
of Chiles 2,635-meter-long suspension bridge to Chiloé
Island early this year is just the start of an arduous and
risk-filled process for the victorious consortium. Since July,
the international team has been working to verify geotechnical
assumptions made by government-appointed engineers before
it can start construction, perhaps in 2008.
Crossing the Chacao Channel, 1,000 km south of Santiago,
the bridge will have two main suspended spans of 1,100 m and
1,055 m. Of three roughly 180-m-tall towers, the southern
one will be sited on land. The central support tower will
rise from a mid-channel rock outcrop and the northern tower
will be located in 25 m of water. The bridge carries Highway
5, which runs from Puerto Montt to Pargua, onto Chacao, located
on the north side Chiloé Island.
A Danish/Chilean Joint Venture led by COWI A.S., Copenhagen,
furnished the conceptual design used for the bidding. But
"we must first confirm the assumptions of this design...and
then complete the design," explains Michael Cegelis,
executive vice president of American Bridge International
(ABI) Coraopolis, Pa., a consortium member. The consortium
holds a 30-year design-build-finance-operate contract. Over
80% of it is owned equally by ABI, Germany's Hochtief A.G.,
Essen, and Paris-based Vinci Group. Two local contractors
share the balance.
During the exploratory phase, due to end this December, "we
will analyze the core samples and validate that the bearing
assumptions...were correct," notes Cegelis. "If
there are fatal flaws...work may be stopped unless there are
corresponding solutions". Then, "we must confirm...the
other assumptions [and] prepare a guaranteed maximum price,"
he adds.
An $18-million bank loan raised by the consortium is financing
current work. If the project is abandoned for technical reasons,
the government will repay the loan. Otherwise, it will be
absorbed into a larger construction loan. "We have a
long way to go but at this point, this seems like a reasonable
endeavor," says Cegelis.
Click
here for In The News archives >>
|