|
| Photo courtesy of St. John's University
|
By Elaine
S. Silver
The author, a freelance writer, lives in the Hudson
River Valley and reports frequently for DesignBuild
and other publications.
When
the 2001 championship St. Johns University mens
soccer team first set foot on their new field last September,
they could be forgiven for feeling that they had received
some extra blessings. After all, the idea for the new soccer
stadium may have had divine intervention.
When Maxine and Jerome Belson traveled
to Vatican City in 1996 with the then NCAA Division 1 soccer
national champions to present a replica of their trophy to
the Pope, the couple got an earful about players injuries
from running around on the existing artificial turf. "It
was my wifes idea to change the turf," says Belson,
a successful real estate developer who has built 50,000 residential
units in New York City. When all was said and done, the Belsons
donated about $6 million for the $9-million project.
The injuries spurred a series of events
that led to the universitys first design-build contract
for an innovative project that fields the first soccer stadium
ever built over a parking deck and one of the first stadiums
approved by the international soccer federation FIFA (Federation
Internationale de Football Association, Zurich) with a new
generation of injury-limiting artificial turf. The stadium
is home to the mens and womens soccer programs
and seats about 2,300 Red Storm fans.
Space Exploration
The unusual design and the design-build
contract were both driven by the universitys need for
more parking. St. Johns University sits in the middle
of the New York City borough of Queens. Space on the campus
is precious and parking for the 2,000 resident students and
6,000 commuter students cannot be disrupted or left under
construction for very long.
The original idea for putting the soccer
field on top of a garage came from Arquitectonica (ARQ), New
York City. "We originally looked at creating the field
and building a parking garage next to it," says Robert
Fatovic, vice-president of ARQ Sports. But that was an expensive
and expansive solution. ARQ then came up with its innovative
solution. "There are parking decks with tennis courts
on top, but not a stadium," says Fatovic. The solution
had other advantages, too. It put the stadium on grade with
a nearby baseball field, creating an elegant sports corner
of the campus. A sports center building now under construction
will link the two sites.
"The board of trustees approved
the concept in July 2001," says Kevin D. Louie, executive
director of design and construction at St. Johns. "Then
we asked The Thornton-Tomasetti Group Inc. and Urbitran Associates
to come up with design solutions." Both New York City
design firms had long-term relationships with the university
and had designed other parking garages on the campus. At this
point, the project was planned as a traditional design-bid-build,
but "we did pay them $10,000 each for their proposals,
so we knew we were getting a real design plan and not just
a marketing proposal," Louie says.
 |
| Innovative garage/stadium was a
solution dictated by tight site and schedule, sports injuries
and need for parking. (Photo courtesy of St. John's University) |
Urbitran won the competition by
coming in on budget by leveraging the terrain. "Urbitran
came up with the scheme of putting 80% of the deck on the
precast inverted-Ts and the other 20% on the grade of the
hill, so we didnt have to do as much excavation work
and had less of a deck that we need to build and purchase,"
says Louie. In the end, St. Johns made aselection based
on the complete package consisting of the cost and the design,
and the integration of the two.
Critical Constraints
Lawrence M. Rosenbloom, Uribitran senior
vice president, first suggested using a design-build contract.
He believed that design-build was a natural choice for this
project because the university wanted the stadium ready in
less than a year, the parking was critical and cost effectiveness
was crucial to the schedule. "We could finish the entire
design and get the bids back and find out that we were over
budget and then have to do it over and have the clock ticking
against us," says Rosenbloom. "So we took on the
responsibility to do design-build." Urbitrans contract
was for a guaranteed maximum price and it teamed with HRH
Construction LLC, New York City.
The design-build arrangement paid off.
The precast order went out three months after Urbitran was
selected. "If we had done the process in the traditional
way, we would not have been in a position to even order the
material until we had gone through the documents and the bids"
says Anthony Rodriquez Pacheco, vice president of facilities
and construction at St. Johns University. "We would
not have made the September 2002 deadline."
Urbitran
took the overall dimensions of the platform, which was dictated
by the soccer stadium requirements, and created a column grid
that maximized the parking below at 300 spaces. St. Johns
athletic department was responsible for selecting the turf,
but had not yet made a decision. So, Urbitran determined the
maximum load for both artificial turf and natural grass. It
came up with a schematic structural plan and used it when
it met with the precaster. This was enough to put together
the shop drawings. "This way, we established the largest
subcontractor cost and finalized the contract with the university,"
says Rosenbloom. The order for the precast components was
submitted in December 2001, although the design for the stadium
was not completed until May 2002.
 |
 |
| Belsons (top picture, left center)
donated funds and helped Red Storm dedicate new stadium
(Photo courtesy of St. John's University) |
The stadium
design continued to be the responsibility of ARQ under a separate
contract with St. Johns. However, ARQ acted as a team
member to the Urbitran and HRH design-build team. Adding to
the partnership, St. Johns athletic department had to
choose, specify and order the turf, bleachers, lights, flagpoles
and scoreboards. Rosenbloom says the design-build arrangement
saved the university five monthsthe time it took the
precast fabricator to create and deliver the parking deck
support systemto finalize the stadium design and decide
on the amenities.
Picking the right turf was a priority.
Fortunately a material called FieldTurf became available around
that time that played like grass, says Erin McDonnell, associate
athletic director. It is a new concept in artificial turf
that combines sand and rubber in a product that looks and
feels like grass. The technology spurred a change in the rules
set by FIFA, which governs soccer around the world. St. Johns
is one of only six facilities in North America to have a FIFA-approved
artificial surface. And its almost maintenance free.
A waterproof membrane covers the deck
of the 90,000-sq-ft single- level parking garage, followed
by an asphalt layer to level it out, a drainage system, and
2 in. of ground-up Nike brand sneakers that looks and feels
like soil and the "grass."
The innovative design solutions mirrored
the flexibility needed by the owner to deal with this new
way of doing business. "There was not a complete set
of documents to work under. We were creating product as we
were going along. It was always an evolving process,"
Louie says.
And it was hard to tell who was who.
"It did take time to figure out the new relationships
and keeping the characters straight," says Pacheco. "The
staff is used to dealing with general contractors or construction
managers. Now we have these [the design-builders] on the other
side of the table sitting with us. One of the issues was:
Who do we talk to? Are we talking to the prime holder of the
contract who happens to be the design professional or are
we talking to the contractor?"
In the
end, what mattered was getting the job got done on time and
on budget. On Sept. 21, 2002 St. Johns dedicated the
new Belson Stadium with the 2001 Big East Champion Red Storm
Mens soccer team and the Belsons on the field.
Click
here for features archives >>
|