|
| Photo courtesy of Kiewit |
By Paul Rosta
The author is a correspondent for the McGraw-Hill
Cos. He lives in Los Angeles, where he regularly
reports on industry issues.
Over the past two decades, the new light-rail line linking
Los Angeles and Pasadena seems to have endured a start and
stop for every one of its nearly 14 miles. But in a remarkable
conclusion to its long odyssey, the $725-million Gold Line
will carry its first customers this July, on time and under
budget, just three and a half years after its rebirth as a
design-build project.
Conceived to ease freeway congestion, the Gold Line started
out as a conventional design-bid-build project under the auspices
of the Los Angeles County Metropolitan Transportation Authority.
Construction was about 12% complete by early 1998 when a financial
crisis prompted MTA to suspend work after spending about $274
million. But strong support in the communities to be served
by the rail lineLos Angeles, South Pasadena and Pasadenapushed
it forward. They wanted to get it done, says Rick
Thorpe, chief executive officer of the Los Angeles to Pasadena
Metro Construction Authority.
In response, the California legislature in 1998 created
a joint-powers authority (JPA) to finish the project, then
known as the Blue Line. (The name was changed in 2001 to avoid
confusion with the light-rail line linking Los Angeles and
Long Beach.) The JPAs success shows that a single-purpose
agency responsible for developing the project, combined with
design-build, really accelerates the process, says Nancy
C. Smith, attorney for the authoritys legal adviser,
Nossaman Gunther Knox & Elliott, Los Angeles.
Money Matters
Thorpes predecessors already had recommended using
design-build to finish the Gold Line. One of the benefits
of design-build is that you dont need as much oversight
as conventional delivery, says Thorpe. Only about 10% of the
budget is going to soft costs, he says. We probably
knocked off 15% of the total cost of the project just in engineering
and administrative costs.
Because the legislation establishing the JPA provided only
the money left when the project was suspended, the JPA had
to secure an additional $40 million in state funds and $35
million from development rights along the alignment. In all,
finishing the Gold Line will cost about $451 million above
the $274 million spent previously.
The project was divided into two main design-build contracts
worth about $300 million. The larger segment, dubbed the Arroyo
Seco, includes 13 stations, 72 grade crossings, track work
and two tunnel sections. To build credibility with the public,
the JPA jump started construction on a highly visible segment,
separately awarding a $21-million design-build contract on
a low-bid basis for a 2,800-ft-long elevated section in Los
Angeles Chinatown. Cambridge, Mass.-based Modern Continental
Construction Co. Inc. and HNTB Design/Build, Kansas City,
Mo., is completing that segment as a team.
Dual Drawings
Procurement for the Arroyo Seco contract was fast-tracked
and consultants raced to develop the proposal in only nine
months, half as long as a conventional process. Thorpe acknowledges
that the mission would have been easier if the project had
been design-build from the start, but he counts as one
of our successes...that we were able to take what we got from
the MTA and convert it into a design-build program.
Before MTA suspended construction, a cost-reduction exercise
had significantly modified some design elements. The JPA asked
two firms, Santa Monica-based Gensler and Gruen Associates,
Los Angeles, to provide conceptual design. The 10% to 15%
design was intended to provide a comfort level without being
so far along that it would tie the contractors
hands, says J.F. Finn III, Gensler senior associate.
 |
| Dual drawings integrated old and
new designs. (Photo courtesy of Kiewit) |
Since thousands of pages of design documents at various levels
of completion already were in hand, developing criteria for
the proposals required special care. We had to make
it clear to the proposers that they were indeed the designer
of record, says Tom Stone, JPAs former chief project
officer who oversaw design and construction from 2000 to 2002
and who now is a consultant on rail projects. The solution
was to distinguish between two categories of design documents:
those representing baseline, or mandatory components
and reference drawings representing parts of the
project open to design-build innovations. I personally
know of no other design-build project that had this...dual
set of drawings, says Dan Duplisea, Kiewit Pacific Co.s
Phoenix-based district manager.
For the Arroyo Seco contract, the JPA received proposals from
teams led by Granite Construction Co., Watsonville, Calif.,
and Herzog Contracting Corp., St. Joseph, Mo.; Kiewit Pacific,
Santa Fe Springs, Calif., and Washington Constructors Inc.,
Boise; Modern Continental/HNTB; and Tutor-Saliba Corp., Sylmar,
Calif. The Kiewit/Washington team came out on top in both
technical categories and price, with a $260-million bid. Duplisea
believes that Kiewits earlier work on the rail line,
including two bridge contracts and a track removal contract,
gave the team a leg up. We knew about every linear foot
of the line before we bid it, Duplisea says. Once in
the field, the Kiewit/Washington team worked so quickly that
a lot of times we joked that this was really a build-design
project, Thorpe says.
An important contract provision requires the JPA to accept
liability for changed geotechnical conditions in underground
sections and the design-build team to assume the same risk
for at-grade sections. It ended up being a really good
decision, Stone says. The only way design-builders
could have accepted the risks of changed conditions was to
put additional money in their bid to cover it. Potentially
challenging sections, such as a 3,000-ft-long tunnel under
some century-old buildings in Pasadena, came off without a
hitch. A far more serious test arose in early 2002 when the
California Public Utilities Commission withheld construction
permits for 21 intersections. Design-build turned out
to be a big challenge for the PUC, Stone says. Theyd
never had to move so fast. Before the commission relented,
the design-build team was forced to hopscotch around
and build in a much less efficient way than [it] had contemplated
when [it] bid on the project, says Habib Balian, JPA
chief administrative officer.
The delay cost three months and $6 million, yet Duplisea
says that the flexibility of design-build enabled the contractors
to mobilize additional crews and equipment and move
to other locations that were not in contention. With
conventional procurement, this could have potentially
stopped the whole job, he says. The PUC episode is an
example of what Thorpe calls the most difficult aspect
of design-buildcoordination with third parties, whether
public agencies or private utilities. If he had it to
do over again, Thorpe says he might hire a staff member dedicated
to defusing potential tensions. Concerned about changes, Thorpe
also urges prospective owners to take your time and...think
through what is important to the community, what is important
to the operator, what is important to the structure.
He suggests a budget line item in case youll want
something different from what the contractor wants to provide
you.
With the Gold Line under its belt, the JPA now is looking
at a proposed $1.6-billion, 24-mile extension to the city
of Claremont. Funding, schedule, and other key issues are
still to be determined. But whatever the future of the line,
Thorpe predicts design-build will be a part of it.
Click
here for features archives >>
|