|
Motown Gushing Over
Design-Build
By Peter Green
The author, a former transportation senior editor for
Engineering News-Record, lives in New York City and
writes occasional pieces for DesignBuild.
Over
the past nine years, the Detroit Water and Sewerage Dept. has
delivered about 30% of all its construction projects through
design-build. The contracts range from a miniscule $1 million
up to a hefty $285 million, with a wide spread of numbers in
between. Much more is on the way.
The driving
force behind the departments construction program is
Awni Qaqish, assistant director of engineering services. Qaqish
now manages a five-year capital budget of $3.2 billion. After
2008, he anticipates another $1 billion in projects at three
water treatment plants. According to Qaqish, that means up
to $1 billion in design-build work is on the horizon.
To handle
the job, Qaqish heads a staff of over 300 for design and management,
which makes the group "the largest consulting firm in
the metropolitan area," he says. And it has been busy.
"We introduced design-build into the departments
program and currently have 20 design-build projects totaling
$1.1 billion either completed, under contract or under development,"
Qaqish says. He estimates that design-build has already saved
the agency about $163 million. "That includes $55 million
in inflation, $90 million in project oversight and $18 million
in engineering efficiency," he explains.
DWSD will
use design-build for a number of projects (see chart), possibly
including installing major water transmission mains, which
could total $90 million. In February 2006 Detroit is hosting
the Superbowl and needs to replace a $20-million water distribution
system around the stadium. "In order to meet schedule
were going with design-build," says Qaqish. "We
did a pilot study last year and determined that design-build
is a viable delivery system for replacing aging water distribution
mains. This will be a first for us."
|
DESIGN-BUILD
PROJECTS UNDER
DEVELOPMENT OR PROCUREMENT
$ millions
|
| Water
meter replacement and automatic meter reading |
192.0 |
| Switchgear
replacement, remote generator control, emergency generator
maintenance |
41.9 |
| Security
systems upgrade for booster pumping stations |
15.3 |
| Two
waste washwater and sludge treatment facilities |
40.5 |
| Marine
terminal warehouse |
20.0 |
| Stadium
water main replacement |
20.0 |
| Sewer
rehab program |
50.0 |
| Communications
program |
128.0 |
| TOTAL |
$507.7 |
DWSD advises
numerous consultants and municipalities on the collaborative
delivery system and Qaqish readily offers some suggestions.
"For design-build to work, you need a well-defined scope,
quality-based selection and the right individual from your
team overseeing the project. You also need to make sure everyone
is pulling together towards the common goal," he says.
Throughout the projects, DWSD holds numerous workshops for
its staff and other project participants on such issues as
scope development, project evaluation, design and training,
Qaqish says. The department also involves its maintenance
and operations staff early. For those new to design-build,
Qaqish suggests starting with a small greenfield project as
a test and "make sure you have a champion for the project.
That way, prestige is on the line, but once successful, everyone
wants to buy in because they see the benefits of faster delivery,
less change orders and it saves money," he says.
Big Boost
As a public utility, DWSD cannot interrupt
service to its customers while upgrading plants and that kind
of work is always going on. "Our infrastructure requires
constant improvement to meet environmental regulations,"
Qaqish says. And with the departments tenfold increase
in the capital program, it had to turn to design-build delivery
to considerably reduce the time between a projects conceptualization
and completion.
 |
|
Qaqish
|
Varying state
regulations have caused problems in implementing design-build
project delivery on the full scope of the departments
projects. It constructs water and wastewater treatment plants,
but state environmental regulatory oversight differs for each
type of service and that affects design-build delivery, at
least for now.
All of
the departments projects require a permit from the Michigan
Dept. of Environmental Quality, but that agency has stricter
regulations for wastewater than for water. To obtain a permit
for wastewater plants, DWSD must submit "biddable plans
and specifications," which makes it difficult for the
utility to achieve the full benefit of design-build delivery.
"DWSD is working with the state to resolve these concerns
in order to allow a wider application of design-build to wastewater
projects," says Qaqish. For water treatment plants, the
state grants permits for design-build projects based on the
generally accepted 30% plans.
Design-build
had a modest start at DWSD with the installation of a lime-mixing
plant at a wastewater treatment plant in the early 1980s.
But in November 1996, DWSD started its wider use of design-build
with a booster pumping station. "In the 1980s, a similar
job would have taken five years to complete. We took 10 months,"
says Qaqish. The icing on the cake is that the station added
40 million gallons per day in sales and the $7.4-million project
paid for itself in three years, he says.
The seven
Water Board Commissioners, who have to approve all engineering
department contracts, were sufficiently impressed with design-build
that they recommended trying it on all future projects. And
thats a tall order.
Although
Detroit isnt a large city, the department serves 126
communities in a 1,000-sq-mile metropolitan area with water
and a slightly smaller area, 700 sq miles, with wastewater
treatment, making it the third-largest water district in the
U.S. DWSD, in effect, functions as a nonprofit business, with
its rate-based revenue equaling its expenditures. The rates
are the fifth-lowest in the country.
The departments
modus operandi for design-build projects starts with identifying
the scope of the work and establishing milestones for the
various stages. With assistance from a consulting engineer,
it develops a request for proposals and meets with each respondent
for a confidential discussion 30 to 45 days before receiving
the technical proposals. "No notes are taken unless an
issue affects both parties," says Qaqish. "Both
sides ask questions and seek clarifications and if the closed
door discussion elicits changes to the sealed financial bid,
the respondent can provide additions or deductions to the
original sealed bid in another sealed envelope."
 |
|
Water utility constantly
upgrading its facilities. (Photo courtesy of Hazen &
Sawyer)
|
 |
|
Pumps are heart of plant that opened
this month.(Photo courtesy of DWSD)
|
After evaluating
and scoring technical proposals, the owner opens the bids
and enters them into the final evaluation process. Detroit
works with a quality-based selection system that generally
scores 40% for technical proposal, 10% for the team and its
staff, 20% for the work plan, 5% for local economic development
and 25% for life-cycle costs, which includes capital and 20-year
lifetime cost.
Design-build
works well in emergencies. When the roof of an underground
concrete reservoir at the Lake Huron Water Treatment Plant
collapsed in June 1999, DWSD had to replace it in a hurry.
The department called in NTH Consultants, Ltd., Farmington
Hills, Mich., to determine the cause of the collapse and to
analyze the economics of repairing the existing reservoir,
razing it and reusing the site, or building anew on an adjacent
site. Charles Roarty Jr., vice president in the firms
Detroit office, says the latter was the best choice, but geotechnical
analysis indicated the adjacent site would need considerable
piling to carry the load.
DWSD also
engaged Greeley and Hansen LLC, Chicago, to assess sizing
requirements for a new reservoir in relation to the capacity
of the treatment plant. The department then retained the two
firms and PMA Consultants LLC, Ann Arbor, Mich., to develop
an RFP and provide oversight throughout the project. Paul
Vogel, principal in Greeleys Detroit office, says the
three firms had three weeks to prepare performance specifications
that would be equivalent to 30% design.
To save
time, DWSD solicited contractors three weeks before publishing
the RFP and identified six local contractors nearest two of
the four companies in the country that specialize in constructing
large wire-wrapped underground concrete reservoirs. Putting
pressure on the six, the RFP required them to submit priced
proposals in less than three weeks.
Four responders
dropped out and the remaining two submitted proposals in 15
days. Then the agency and its consultants in a round of all-night
sessions evaluated the remaining two proposals and awarded
a $37.3-million contract to EBI Detroit Inc., which had engaged
the Detroit office of Finkbeiner, Pettis and Strout Inc.,
to design the project.
"We
saw the urgent need and started some of our preparations,
with the cooperation of the departments consultants,
in order to offer about 70%-complete design in our proposal,"
says Robert Schimmel, EBI president. The jump-start was necessary
for the contractor to attempt to put a 30-million-gal-capacity
below-grade reservoir in service in 11 months.
Quick Response
Speed was needed and delivered on other
projects. In December 1998, DWSD signed a $285-million design-build-maintain
contract to replace a 1920s water treatment plant in Waterworks
Park. The new plants 240-million-gallons-per-day capacity
sets a record for public water or wastewater design-build
projects in the U.S., says Qaqish. It opened this month.
DWSD engaged
Hazen and Sawyer PC, New York City, as its consultant to assist
with developing a performance-driven RFP and evaluate proposals.
"The RFP asked for major equipment without naming brands,
specified capacities and called for redundancy and full automation
in the equipment," says Alexander Varas, vice president
in the firms Detroit office. Three teams responded and
the owner selected DWT, a joint venture with Black & Veatch,
Overland Park, Kan., Montgomery Watson Harza, Broomfield,
Colo., Walsh Construction, Chicago, J.S. Alberici, St Louis,
and Motor City Electric Co.
Hazen and
Sawyer previously had worked as a consultant for DWSDs
design-build projects. Varas says he prefers working for an
owner rather than as a partner in a joint venture that takes
a financial risk.
In 1999,
DWSD, like many other firms, thought that the much-heralded
Y2K crisis could affect its power supply. To protect its vital
services, the department required that 52 emergency generators
totalling 88 Mw be installed at 13 sites. The department awarded
a $52-million design-build contract to Motor City Electric
Co., which served as prime contractor to supply and install
the generators. The contractor engaged the local office of
Tetra Tech MPS to design the installations.
The RFP
required the generators to be running by January 1, 2000.
Starting in May and working at all 13 sites simultaneously,
Motor City completed the job in December 1999.
Motor City
Vice President Paul Gillespie thinks design-build is great.
"All people involved, including the owner, work as a
team," he says. "They arent worrying about
protecting their own interests. And working as an at-risk
contractor, hiring a designer with whom we have had a good
relationship works well since we know ahead of whats
coming up."
Click
here for features archives >>
|