|
Track Team Tames Tough Australian Outback
By Mary Buckner Powers
A 16-year McGraw-Hill veteran, Powers has reported
on a number of design-build projects in DesignBuild
and its sister publication Engineering News-Record.
 |
|
(Photo courtesy of KBR)
|
After
100 years of planning and several false starts, the final
leg of the north-south cross-Australia railway finally is
nearing completion. The landmark project, meant to celebrate
the countrys centennial, came together when a design-build
consortium pushed design to overcome harsh conditions while
keeping costs in check.
The $715-million, 1,420-km line connects the
town of Alice Springs to Darwin, the closest port in Australia
to Asia. It traverses the sparsely populated Northern Territory
through the Macdonnell Ranges, Tanami Desert and tropical
woodlands. The project also includes operation and maintenance
of an older line that runs 835 km south from Alice Springs
to Tarcoola, tying the new line into an existing rail system
that links all of the continents major coastal cities.
Booting Up
Leading the rail consortium is Houston-based Kellogg Brown
& Root (KBR), considered the catalyst that made the project
happen, says Franco Moretti, former CEO of Asia Pacific Transport.
APT holds a deed from AustralAsia Railway Corp., which was
established by the Northern Territory and the South Australian
governments to push the design, build, own, operate, transfer
(BOOT) project. APT is 50% owned by KBR. Other partners include
three Australian contractors.
APT, in turn, formed ADrail,
which includes KBR, John Holland Group, Barclay Mowlem and
Macmahon Holdings to design and build the system and Freightlink,
which includes Australian Railway Group and South Australia
Northern Territory Holdings, to operate and maintain the line
for 50 years.
One responsibility of the
organizations is developing the market for the new line. We
have to identify the market, size it and win it, says
Moretti. APT divided the potential market into two components.
One is the freight market within Australia. The other is international
trade fostered by the railways link with a new deep-water
port under construction in Darwin that will handle freight
to and from Asia. The financing was related to how we
segregated the two, so we have strong incentives to develop
both businesses, says Moretti.
The complex deal took two years
to negotiate and had 25 parties and 112 signatories. Private
investors committed $480 million and Australian governments,
which include the Commonwealth and the two territories, committed
the remainder. A cornerstone was a set of guidelines negotiated
with the Commonwealth allowing companies wanting to compete
with the concession holder access to the railway. It
was fundamental to allow the project to proceed, says
Moretti. Click
here to view map
KBR began putting the team
together in 1997 and construction started in 2001. The
project needed companies that had experience in remote construction,
civil construction and earthwork and they had to be able to
self-perform, says Moretti. Each firm has critical expertise.
John Holland Group, Melbourne, is the largest bridge builder
Down Under; Barclay Mowlem, Pymble, has a significant rail
division; and Mcmahon Holdings, Welshpool, is a large earthmoving
outfit.
Under the BOOT agreement,
the consortium had just three years to build the line and
get it into service. Land acquisition was not an issue. The
rail corridor is owned by the Crown and indigenous land trusts,
similar to U.S. Indian reservations. The necessary surveys,
investigations and design to develop the link were done in
1981. The government also provided quarries for materials
needed in construction.
Penny-Pinching
 |
| Railroad construction teams had
to bring virtually everything with them as they pushed
across the Outback. (Photo courtesy of KBR) |
Finding the most efficient construction methods for the remote
locations and the widely varying topography and weather were
critical issues. There is little access to construction materials
and equipment in the Outback. The population of the Northern
Territory, which is twice the size of Texas, is only 200,000.
Alice Springs, population 31,000, is as far from the nearest
big city, Adelaide, as it is from Darwin, a city of 70,000.
Darwin is closer to Singapore than it is to any city in Australia.
There are two intermediate towns, Katherine, with 9,000 people,
and Tennant Creek, which has 3,000. This is 10 years
worth of work for the Territory, says Charles Duncan,
ADrails design manager.
Otherwise, the rail job is
straightforward. Were not pushing the bounds of
technology in railroad engineering. We were driven by our
desire to find clever ways to do ordinary engineering quicker
and cheaper, so the design effort was aimed at questioning
traditional ways of doing things, says Duncan.
The project had to be built
within a tight budget to make it viable. It only got
off the ground by the skin of its teeth, so we were pushing
the limits of good practices to save costs, Duncan says.
The $715-million budget is about two-thirds of the normal
cost of a railroad of that size.
Shaving Costs
Many decisions that may not affect costs much on a small
project became significant on this one. The team decided to
place railroad ties 60 mm farther apart than normal and shaved
100,000 units off the job. We just trimmed around the
edges, says Duncan. Another major decision was to reduce
the depth of the ballast from the standard 250 mm to 150 mm.
The thickness eventually will be increased during routine
maintenance, deferring the cost until the line is operating.
Huge costs were also saved
on the 510-m bridge across the Elizabeth River, near Darwin.
Constructors were concerned that they could not build it within
the schedule and early estimates put the cost at $15 million.
The bridge eventually was built alongside an existing highway
bridge, which simplified the railway structure and allowed
the lateral load to be shared between the two bridges. The
cost was reduced to $6 million and the schedule was met.
All of the design solutions
were driven by construction requirements, says Duncan. We
developed a smart set of standard bridge designs with interchangeable
components that worked successfully, he says. The project
includes about 100 minor bridges and 7 major bridges. Small
bridges were all built with 12-m prestressed concrete spans
and large bridges had 30 m spans. The sizes and weights were
picked so they could be transported without a highway escort.
In most areas of the desert,
there was no historical information on hydrology. Contractors
could decide during construction whether a small bridge or
a culvert was most appropriate for the dry streambeds and
catchments that flooded during infrequent but torrential rains.
They also used method specs for varying terrain. It
gave crews true flexibility and maximized the borrow material,
says Al Volpe, ADrails project director. A geotechnical
crew worked ahead of construction, selecting materials and
doing compaction tests.
The project required about
1,400 culverts. The 1.8-m-diameter culverts were manufactured
on site out of rolls of steel plate to avoid having to truck
in precast concrete units.
Everything was standardized
and refined with a production line mentality, says Jock Chudacek,
design and construction manager for ADrail. Chudacek kept
tight control on design and its timeline. The design shop
was set up completely separate from the four design and construction
companies involved in the project. It was done at a
distance for results and communication, Chudacek says.
It also kept team members away from the external influences
and selfish motivations of the parent company. That
does happen in joint ventures, he says. He also required
designers to be 100% devoted to the railway project and not
also assigned to other jobs by their employers.
All drawings had to be approved
by 10 stakeholder companies, each of which assigned a representative
who was a renowned expert, notes Chudacek. So when they
required something, it was for a reason, not a want,
he says. Supervision by this committee worked well because
the members were so well respected.
The project was on a fast track
and design was never more than a few weeks ahead of the bulldozers.
The earthwork was mobilized on the day the concession was
signed, says Chudacek. Twelve months of planning went into
the project before that day. We had a small construction
team that convinced the partners to put in the necessary resources
to be ready to start quickly, says Kevyn Brown, ADRail
construction manager.
Four Fronts
 |
| Rails were welded into 357-m lengths.
(Photo courtesy of KBR) |
The key to the projects success has been the planning,
says Volpe. Originally, the team thought the line would be
built from Alice Springs north to Darwin. But plans changed
to save time. Construction depots were set up at the two intermediate
towns, Tennant Creek and Katherine, giving constructors four
work fronts. Earthwork progressed simultaneously north and
south from each town. Each earthwork site had two 10-hour
shifts a day for 13 days a fortnight. Each shift built 1 km
a day.
Ballast was produced at a quarry
north of Katherine. About 2 million railroad ties were manufactured
at plants in Katherine and Tennant Creek. Rail was trucked
from a steel mill in Whyalla in 27.5-m lengths to both towns,
where they were welded into 357-m lengths. Two work trains
were loaded everyday with ties and six pairs of rail and rolled
out to the working front. The two tracklayers worked toward
each other from the two towns. After meeting last December,
they headed south from Tennant Creek toward Alice Springs
and north from Katherine to Darwin.
Construction was scheduled
around the 3-1/2 month rainy season in the north and around
the three weeks of torrential rains in the desert. Nothing
could stand in the way of working continuously, says
Volpe.
Work camps were set up every
100 km so the maximum travel each way for workers was 50 km.
Mobile machine workshops were built and wells were dug for
both drinking water and construction water. There was
no infrastructure, says Alan McCann, ADRail logistics
manager.
Every six weeks, workers had
a week off. We had to fly everyone to where they were
from, at least 2,000 km away. Thats what happens in
Australia, says McCann.
But good planning has produced
good results. The track laying will be complete Sept. 15,
5-1/2 months ahead of schedule. Operations should begin by
the end of the year. Weve had some close calls,
but weve squeaked by, says Volpe.
Click
here for features archives >>
|