 |
|
(Photo
by Jim Sullivan Photography)
|
Hartsfield Runway Spans Interstate
By Victoria L. Tanner
The author has provided communications
services to the industry for more than 20
years, working with general contractors,
subcontractors and trade groups.
Scarlett OHara and Rhett Butler
have long reigned as Atlantas brashest couple, but once
Kathryn Masters and David Casey finish the ambitious construction
project theyre leading at Hartsfield-Jackson Atlanta
International Airport, OHaras and Butlers
title may well be gone with the wind.
Masters
and Casey are involved in building a critical component of
Hartsfields new 9,000-ft-long 10/28 runway, the centerpiece
of a $5.4-billion airport expansion. Their massive $159.5-million
bridge structure will permit the runway to cross over Interstate
285, allowing planes to take off and land literally atop the
busy road.
The bridge
configuration is believed to be unique. It will span 10 lanes
of traffic but allow for eventual expansion of the road up
to 18 lanes. The bridge is so vast that the support structure
will create a tunnel, although none of it is underground.
The structure will be the first roadway tunnel in Georgia.
"When
I first took over the project and they told me it was design-build,
I thought it was going to be a disaster," says Masters,
senior project manager for International Aviation Consultants,
the joint venture providing program management services to
the City of Atlanta and its Dept. of Aviation for the five-year
expansion project. "The city has never done a design-build
like this," Masters says. The projects intense
schedule made design-build a logical choice, although she
acknowledges that city officials have "found it very
difficult to give up control" under the design-build
paradigm. IAC is comprised of Parsons Aviation, Rosser International,
H.J. Russell, Turner Associates and URS Corp.
Masters
knew that the projects proximity to state roadways also
would require a close working relationship with the Georgia
Dept. of Transportation (GDOT), another agency with limited
knowledge of design-build project delivery. "Ive
always thought this job was like having two novice owners,"
says Masters. She worried that GDOTs internal structure
was not well suited to the demands of the jobs fast-track
schedule, fears that so far have not materialized. Since the
jobs kickoff in early 2003, the team and the project
have come together quickly. "Its gone very well
so far," says Masters. "Were on schedule and
on budget."
For the
design-build team, juggling tight schedules and budgets is
just part of the process. But coping with the unique design
and engineering demands of the project raises the stakes considerably.
The structure incorporates a main runway bridge that measures
1200 ft long and 486 ft wide, and a 450-ft-long, 450-ft-wide
taxiway bridge. Casey, program manager for Archer Western
Contractors Ltd., Atlanta, leads the design-build team. The
Atlanta office of Parsons Brinckerhoff Quade and Douglas Inc.
is the teams lead design engineer, while Heath &
Lineback Engineers, Marietta, Ga., is handling the projects
structural design.
The design-build
team did extensive preliminary engineering work as part of
a 15-month pre-bid process in which the city conducted workshops
for potential bidders to learn about the job and exchange
ideas and information as the request for proposals was being
developed. "I think a lot of good things came out of
that process," says Casey. "The city looked for
everyone to bring out the things that were going to cause
significant issues later on." Masters says the process
allowed bidders to "ask questions without giving away
the farm."
The pre-bid
process also gave the design-build team the opportunity to
study the minutiae of the citys preliminary plans. "The
hardest part in the pre-bid process was determining what would
and would not be accepted as being responsive to the RFP,"
says Gary Lineback, senior structural engineer at Heath &
Lineback Engineers.
The RFP
featured a 35% design concept developed under a separate city
contract. The preliminary designs were used primarily to familiarize
various agency groups with the overall concept for the bridge,
thus helping to pave the way for the design-build process
as it moved forward. Specifics of the drawings were not expressly
written into the RFP "because we felt there was no need
to be so dictatorial," Masters says. However, the city
did have "eight non-negotiable items," including
essential criteria like the number of lanes of traffic to
be accommodated. Beyond that, bidders were given a wide berth
in preparing their proposals. "The RFP allowed for quite
a bit of innovation," says Archer Western project manager
A. Steven Hausler Jr. "And we went for it."
Load Limit
 |
|
Massive precast
concrete beams will help carry 747s and A380s over I-285.
(Photo
by Jim Sullivan Photography)
|
Lineback shouldered considerable technical
burden. The load standard for the entire runway was set at
1.4 million lb. The bridge was required to handle loads created
by aircraft, such as the Boeing 747 (at 1.04 million lb) and
the Airbus A380 (at 1.33 million lb). Variations in aircraft
wheel configuration also had to be factored into the design
equation, as well as the impact and influence of loads and
force created by shear.
Given the
set of variables, Lineback realized that his design would
require a unique solution. "I dont know of any
place in the world to have a project like this that is as
big or as high," he says. Linebacks design features
764 "T-shaped" precast concrete beams with a total
length of 90,000 ft. The beams are 81 in. tall and vary in
length from 94 to 133 ft for both the runway and taxiway bridges.
The combined bridge decks total 725,000 sq ft and will contain
approximately 37,000 cu yd of concrete. The bridge structure
consists of 430,000 sq ft of cast-in-place and precast walls.
The runways interior substructure features solid concrete
walls measuring 3.25 ft in thickness and varying in height
from 35 to 60 ft.
 |
|
State's first tunnel
will carry big jets on its roof. (Photo
courtesy of Archer Western Contractors LTD.)
|
Given the
nature of the tunnel structure, the Archer Western team knew
that the life-safety systems required for the project would
be a major cost component. Turning to the design expertise
of Parsons Brinckerhoff, the team undertook a comprehensive
ventilation study to determine the best methods for complying
with code. "Going into the bid, we were looking at ways
we could make the biggest impact with innovative design,"
says John Durand, PB project manager. "We did extensive
computer analysis, with real-time models of the ventilation
and we modeled the evacuation of people in there as well."
Based on
the studys findings, the team developed its proposal
around a dramatic decision to eliminate a conceptual false
ceiling that was in the plans. "It was in the RFP with
a note that it was there for ventilation purposes only and
in our ventilation analysis we decided it wasnt needed,"
Casey explains. The Archer Western teams proposal provided
the city with documentation supporting its argument. "We
saw eliminating the ceiling as a very good opportunity to
save money so we attacked that pretty heavily. We were able
to reduce the number of fans that were placed in the tunnel
to forcibly evacuate smoke by utilizing that ceiling space,"
says Durand. The resulting design features a life-safety system
that includes 10 jet fans, 12 egress doors, emergency power
generation, 4,968 light fixtures, 120 carbon monoxide detection
monitors, a fire protection system and video monitoring. Casey
acknowledges that the extensive pre-bid design work came with
a high price tag. "The risk is so much higher, with no
chance to recoup those costs," he says.
The city
prequalified five firms to participate in the two-part, technical
and price, bid process. Once it reviewed the technical proposals
and deemed them responsive to the RFP, bids were opened and
the award was made to the low bidder. Only two teams submitted
final bids and the award created considerable controversy.
Landmark
The Archer Western bid was approximately
$20 million below a bid submitted by 5R Constructors LLC,
Atlanta, a partnership of S.W. Matthews, APAC Georgia and
Michael Thrasher Trucking. 5R Constructors already is working
at the airport with a $350-million earth-moving contract that
involves transporting 27 million cu yd of earth to the runway
site. After losing the bid, 5R Constructors filed suit in
federal court, seeking a temporary restraining order to stop
work. It claimed that the winning bid was not responsive to
the RFP. U.S. District Court Judge Owen Forrester denied the
request and cleared the way for the city to ink its deal with
Archer Western in early December 2002. No further legal action
is planned, says George Wenick, an attorney with the Atlanta
law firm of Smith, Currie & Hancock LLP, which represented
5R Constructors.
The Archer
Western team credits its advance work in the engineering design
for giving them the winning edge. "I would say our team
out-engineered the other team in many ways," says Durand.
"One of them was ventilation, one of them was the innovative
superstructure design, and then there were a lot of smaller
items." Besides besting 5Rs numbers, the winning
bid was $80 million below the citys initial estimate
for the project.
But perhaps
more importantly, the extensive advance design work allowed
the Archer Western team to hit the ground running once the
contract was awarded. Durand estimates that under a traditional
design-bid-build approach, the tunnels life-safety systems
alone would have required approximately two years of design
work. The design-build approach brought the project to 95%
design completion in approximately seven months.
Even as
the project kicked into high gear, the advance work continued
to pay other benefits as well. The lengthy pre-bid timeframe
also created an opportunity for the bidders to forge strong
relationships with the various state and local agencies involved
in the project, which have paved the way for a smoother transition
into the design-build relationship. "They developed a
lot of trust in the design-build team," says Lineback.
"And that has helped us all."
 |
|
Cast-in-place concrete
tunnel wall rises alongside busy Interstate 285 to support
new runway. (Photo
courtesy of Heath & Lineback)
|
With design
nearly complete, Archer Westerns construction team,
which is self-performing approximately 55% of the construction
work, now bears the burden of maintaining the projects
accelerated pace. Completion is scheduled for February 2006,
with commissioning set for May 2006. Casey says his team is
up to the challenge. "This is going to be a landmark
project in this city," he says. "Everybodys
going to see it and we all want to make sure that everyone
knows that it was a quality project that all of us worked
together to achieve."
With the
busy jobsite humming behind them and 10 lanes of traffic rushing
past, Masters and Casey survey the work with an unmistakably
proprietary air. They know it just might be one of the highlights
of their relatively young careers and theyre clearly
proud of what they are achieving. "After this job, theres
not much more you could hope for," says Masters.
But Casey
has high hopes that this project will pave the way for future
design-build opportunities. "Hopefully, the city will
recognize the savings that it got on this project," he
says. "By putting it out there and letting the industry
say these are our innovative ideas, instead of
restricting it to the ideas of just one engineering firm that
theyve hired, we hope they will see the savings and
use this innovative method of procurement again." Casey
adds, "There will be other opportunities. [Design-build]
doesnt fit for every project, but where it fits, I hope
theyll see the benefits [of design-build] in terms of
innovations and savings for the taxpayers."
Click
here for features archives >>
|