|
High-Rolling Monorail Unlocks Las Vegas
Strip
By Paul Rosta The author
is a correspondent for the McGraw-Hill
Cos. He lives in Los Angeles, where he regularly
reports on construction industry issues.
Las Vegas newest wonder boasts no fabulous stage shows,
high-stakes games of chance, or exotic themed attractions.
Instead, the glitzy desert city is about to get a public transit
system befitting its reputation for spectacle. Early next
year, a fully automated $650-million monorail will start whisking
visitors quickly through the heart of this fast-growing metropolis.
Behind
the 36 sparkling rail cars and their four-mile-long elevated
concrete guideway stands an innovative private financing package
and a turnkey design-build-operate strategy. In a probable
first for a U.S. public transit project, "the private
sector stepped up and basically built this," says Todd
Walker, spokesman for Transit Systems Management, the monorails
program manager.
"That
just doesnt happen on a transportation project, where
you have the private sector come in and build a project of
this magnitude," says Jim Cramer, project manager for
Ft. Worth, Texas-based Carter & Burgess Inc., the design-build
teams engineering consultant.
To a large
extent, it was the financing that drove design-build delivery
for the monorail, say project officials. In a scheme compared
by project team members to toll road construction, the monorail
is funded solely by revenue bonds that cover all construction,
equipment, systems and financing costs. The bonds will be
repaid by advertising at the stations and from fares paid
by a projected 20 million passengers annually.
For such
a financing plan to win the confidence of the bond market,
"costs must be known up front," says Tom Stone,
president of Transmax Group, a Las Vegas-based consulting
firm that worked with TSM to develop the monorail. That requirement
pointed to design-build and its power to guarantee a price
in advance, Stone says.
 |
|
(Photo by Michael Goodman for Design
Build)
|
Because
the unorthodox financing strategy limited the availability
of funding during preliminary design, the monorail "probably
could not have been done on any other basis than design-build,"
says Dave Malutich, area manager for Granite Construction
Co., the design-build teams general contractor. Watsonville,
Calif.-based Granite joined with majority partner Bombardier,
the teams Montreal-based supplier of train vehicles
and systems for the project.
"Theres
nobody that is going to step up and plunk down $15 million
to $20 million to design a job like this and then find out
you cant finance it," Malutich explains. Instead,
the team got "enough preliminary design work done that
we felt comfortable putting a guaranteed price on it."
Although
the futuristic monorail seems bound to lure tourists, transportation
officials are counting on it to be much more than just another
attraction. "The monorail is primarily intended to improve
mobility and air quality in our resort corridor," says
Jacob Snow, general manager of the Regional Transportation
Commission of Southern Nevada. After years of staggering growth
and a concentration of service jobs in the Las Vegas resort
corridor, "we are on the edge of stultifying gridlock
and we need to do something about it," he says.
 |
|
Monorail now connects six hotels and
convention center, alleviating gridlock conditions on
the strip. (Photo courtesy of Gensler)
|
If successful,
the project could anchor a proposed 18.5-mile line linking
the resort district to downtown Las Vegas and McCarran International
Airport. Bombardier and Granite also will team on the monorails
next phasea $450-million, 2.5-mile extension that will
draw on federal funding as well as the revenue bonds that
funded the first phase. Depending on when Congress releases
$300 million in grants and loans, construction on the next
phase should begin in 2004 or 2005, says TSMs Walker.
Good Odds
The new line is the offshoot of a privately
funded, two-station monorail that links the MGM and Ballys
resorts on the Las Vegas strip. That shuttle, completed by
Bombardier and Granite in 1995, carries an estimated 5 million
passengers annually and provided a successful test of a longer
route. The new segment expands the monorail with stops at
four more hotels plus the Las Vegas Convention Center.
The innovative
financing and delivery emerged from a search for alternatives
to developing and funding large-scale public transportation
projects, says J.F. Finn, senior associate with the Santa
Monica office of Gensler, the design-build teams project
architect. In 1997, the Nevada legislature authorized Clark
County to award a franchise for a monorail to a consortium
of major Las Vegas resorts. The Las Vegas Monorail Co. owns
and operates the system under supervision of a five-member
board appointed by the governor. TSM serves as the companys
program manager, overseeing design, construction and daily
operations. After several years of discussions and preliminary
design, the Bombardier/Granite team received a notice to proceed
for a design-build-operate-maintain contract from Las Vegas
Monorail Co. in September 2000.
The complex
financing package is split into several levels $450
million in AAA-rated bonds, or "first-tier" debt;
$150 million in second-tier bonds; and $56 million in bonds
held by the sponsoring hotels and the contractors. The design-build
teams stake in the funding provides "an incentive
for them to build on time and on budget" and makes other
bondholders more comfortable, says Walker.
Single-point
responsibility ensured that there would be "no potential
for cost overruns that would have to go back to the resorts
and the taxpayers," says Transmaxs Stone. Bombardier/Granites
contract, currently valued at about $345 million, includes
a $27.4-million contingency account, says TSM President Cam
Walker. "When youre going to private-sector markets
for capital, its very important to control risk and
put dollars" in potentially risky areas, he says. "Im
happy to say we didnt touch the construction contingency,
we didnt touch the owners contingency."
Bombardiers
operations and maintenance contract calls for three five-year
renewable terms. "Theyre warranteeing the system
by operating and maintaining it," Todd Walker explains.
To further boost investor confidence, Las Vegas Monorail Co.
retained two additional oversight consultants, Las Vegas-based
G.C. Wallace Inc. for engineering and Booz Allen for the system
and vehicles, Stone explains.
 |
|
Station design started before property
acquisition. (Photo courtesy of Gensler)
|
Stone contends
that single-point responsibility with the design-build contractor
was the best way to handle the monumental job of handling
dozens of contracts and thousands of interfaces among contractors,
designers, subcontractors and consultants. "By placing
control, definition and execution of these elements in one
place, nothing falls through the cracks," Stone says.
"Theres no finger-pointing."
To Cam
Walker, TSMs president, the biggest challenge "was
the fact that we are building something that is four miles
long." Tasks included securing over 50 permits, negotiating
with private property owners and building the stations, guideway
and operations and maintenance facility. "From a design-build
perspective, it was very helpful that all that was wrapped
up in one contract," he says.
Once the
design-build team gets the green light, "time is everything,"
Malutich says. "All the moneys been borrowed at
the start of the project, so you want that projects
duration to be as short as possible," he adds. Cramer
speculates that "if we werent doing this under
a design-build concept, construction would probably just be
getting going."
Standing Pat
Malutich describes the project as "a
real fire drill" because permitting, construction and
design all had to happen simultaneously. As soon as Granite
placed the superstructure, "the Bombardier people [would]
come in and install all the systems. Thats probably
been the most strikingly effective part of it," says
Stone.
For the
construction and design team, design-build made the job both
harder and easier, says Malutich. It was harder "because
there was so much going on" simultaneously, he says.
Yet it also was easier because the process makes it possible
to catch potential problems early, he adds.
 |
|
Guideways will carry four-car trains
that could reach 50 mph and run the entire route in
about 15 minutes. (Photo courtesy of Gensler)
|
"I
think its a fact that design-build is not the cheapest
way to design a job, or necessarily even to build a job,"
Malutich says. But any inefficiencies that may result from
the accelerated pace "are way offset by the benefit of
having the project done earlier," he says. With conventional
procurement, "Id say that youd easily be
looking at 12 to 18 months added time," he estimates.
Fast tracking
also created significant challenges for the design team. Because
property agreements were still under negotiation while the
designers developed the stations, the team "had to try
to guess at what the requirements for each station were going
to be," says Genslers Finn. Bombardier continued
development of the systems highly sophisticated control
and communications systems during station design, so "the
final requirements [for the stations] were constantly under
refinement," Finn says.
During
construction, the design-build process provided the flexibility
to deal quickly with unexpected conditions. The foundation
design for the projects 54,000-sq-ft operations and
maintenance building originally called for spread footings.
When excavation revealed less competent material in one corner
of the footprint, engineers quickly redesigned the foundation
with drilled caissons.
 |
|
Monorail will run 365 days a year between
the Sahara and MGM casinos and ridership may reach 20
million. Photo by Michael Goodman for Design Build)
|
The episode
illustrates that "when youre sitting right there
with the engineer, when something does go wrong or is different
from what you expect, you can react pretty quickly,"
Malutich says. "Its very critical to have everyone
on site and essentially in the same office," he says.
"Theres just no substitute for being able to walk
down the hall and grab the right guy by the collar and make
him address whats on your mind."
Although
design-build helped ensure that the modification made no dent
in the project schedule, Cramer says the event also illustrates
a potential limitation. The funding available before the notice
to proceed allowed design to reach only about the 10% level,
he says. "Given my druthers, the design would have been
a lot more advanced prior to that", he says. For example,
further geotechnical investigation might have headed off surprises
like the building foundation.
From the
owners perspective, design-build undoubtedly proved
a success, says TSMs Todd Walker. He reports that change
orders of just a few dozen were a fraction of the hundreds
that would ordinarily be expected on a large-scale transportation
project. Cam Walker concurs. "Im extremely pleased
with the execution of our design-build contract and the ability
of it to limit the claims and the issues that need to be resolved
in the partnering process," he says. "Im happy
to say we have no claims out there."
Click
here for features archives >>
|