|
Demonstration Project Saves Lives and Time
By Tony Illia
A number of haunting, painted wood
crosses decorated with roses, ribbons and photos lines U.S.
Highway 70 meandering through New Mexico's Hondo Valley. They
are called descansos, the Spanish term for a roadside memorial,
and the lovingly fashioned markers commemorate the loss of
a friend or family member from an automobile accident. Now,
thanks to a design-build demonstration project, descansos
may become a relic of the past.
Over the past five years, there have been 26 fatalities on
a 38-mile section of U.S. 70 between Riverside and Ruidoso
Downs. The two-lane road plays a key role in New Mexico's
southeastern transportation grid, passing through six counties
and several large cities. Currently, about 4,027 vehicles
a day travel the narrow winding stretch of highway, with commercial
trucks accounting for 22% of the traffic. The vehicle volume
is expected to increase to 6,222 vehicles daily by 2024. U.S.
70 is specifically identified in the state's long range comprehensive
transportation plan as one of 12 priority corridors in need
of improvement.
|
On June 18, 2002, the New Mexico Dept. of Transportation
(NMDOT) embarked on a major widening effort by awarding a
$129.5-million, lump-sum, design-build contract to Sierra
Blanca Constructors, a joint venture of Granite Construction
Co. Inc., Watsonville, Calif.; Sundt Construction Inc., Tucson,
Ariz.; and James Hamilton Construction Co. Inc., Silver City,
N.M. Other team members include URS Corp., San Francisco,
as lead designer, and The Kleinfelder Group Inc., San Diego,
as geotechnical engineer. The work is one of two design-build
demonstration projects approved by the New Mexico State legislature
in 1999.
Championed by former transportation Secretary Pete K. Rahn,
House Bill 506 allows NMDOT to test design-build's effectiveness
as an alternative delivery system in two sample cases between
fiscal years 1999 and 2003. Authorization to use federal funds
on the projects was given by the Federal Highway Administration
(FHwA) under the Special Experimental Projects No. 14 (SEP-14)
process. The other design-build test project was a $20.7-million,
2.32-mile-long widening of N.M. 528 in Rio Rancho, which finished
two months early in October 2003. A.S. Homer Inc., Albuquerque,
and Wilson & Co., Engineers & Architects, Albuquerque,
served as the design-build team. "The authority was very
broad so we could choose any two projects as long as they
would be representative of other projects in the state,"
says Rahn, who now serves as vice president of government
relations for Contech Construction Products Inc., Middleton,
Ohio. "Using design-build on the U.S. 70 project will
save us up to two years compared to the traditional design-bid-build
approach."
Sierra Blanca won the contract despite being $15.6 million
higher than a low-bid submission from the team of HBG Flatiron
Inc., Longmont, Colo., and Ames Construction Inc., Burnsville,
Minn. The lengthy review process weighed proposals based on
qualifications and construction approaches, with an emphasis
on environmental sensitivity and working with communities.
Over 400 properties border the U.S. 70 project and there are
no alternate routes through the valley. "We didn't choose
the lowest bidder," Rahn says. "We actually ended
up choosing the second-highest price. But in our assessment,
we felt that Sierra Blanca's proposal had the least amount
of risk to the state and was most responsive to the environmental
impact statement."
Sierra Blanca also beat out proposals from Hondo Valley Constructors,
a joint venture of Twin Mountain Construction II Co., a division
of Peter Kiewit Sons' Inc., Omaha, Neb., and Parsons Transportation
Group Inc., Pasadena, Calif.; Team 70, consisting of FNF Construction
Inc., Tempe, Ariz., and DMJM+Harris, a unit of AECOM Technology
Corp., Los Angeles; and US 70 Rio Hondo Constructors, a joint
venture of Nielsons Skanska, a unit of Skanska Inc., Whitestone,
N.Y., and A.S. Homer Inc., Albuquerque.
The winning Sierra Blanca proposal had a 30-year asphalt
pavement design life as opposed to the 20-year lifespan of
its competitors. Sierra Blanca also opted for a mechanistic-empirical
design method that uses the same concepts found in the "2002
AASHTO Guide for the Design of New and Rehabilitated Pavement
Structures." Essentially, it utilizes optimally engineered
asphalt materials in specific layers to prevent pavement failure.
"The M-E method relies on material load carrying capability
rather than layer coefficients, which can sometimes be a poor
correlation to the actual load," says David B. Smith,
Sierra Blanca's project manager. "It was a significant
element of our design-build proposal that clearly helped us
land the project."
Speed Bumps
As it stands, the 28-month undertaking calls for widening
the rural two-lane road to four lanes, with 22 dedicated left-turn
lanes. The job requires approximately 800,000 tons of plant
mix bituminous pavement with 650,000 tons of base course material.
There also is a newly configured U.S. 380 intersection with
separated east and westbound lanes, plus a landscaped median
and scenic pullout. About 15 descansos will be saved and moved
as part of the widening project.
The Hondo Valley's cultural attractions and 92 archeological
and historical sites from Mogollan, Hispanic and European
cultures also made highway design a challenge. The area is
perhaps best known for the Lincoln County Wars in 1878-1881,
which enhanced the reputation of outlaw William "Billy
the Kid" Bonney. Under a NMDOT mandate, Sierra Blanca
Constructors must obtain community design approval before
any construction can begin, which means breaking up the work
into six sections.
 |
 |
|
Gabion basket
walls shore hillsides in tight spots.
|
The project got off to a bumpy start with a legal challenge
to the environmental impact statement (EIS) produced for NMDOT
by Parsons Brinckerhoff Inc., New York City. Filed in federal
district court in Albuquerque by the Valley Community Preservation
Commission (VCPC), a local conservation group, the complaint
alleges that construction activities will cause irreparable
injury to natural and historic resources. NMDOT replied that
$35 million was being allocated for minimizing construction
impact and that onsite environmental quality inspectors were
being used. VCPC also claims that FHwA's approval of the EIS
violates the National Environmental Protection Act and Section
4(f) of the Dept. of Transportation Act by ignoring possible
conflicts of interest and alternative routes. "The injunction,
if granted, would have stopped the U.S. 70 expansion project
until the FHwA adequately studies the project impacts on cultural
and historical resources in the Hondo Valley," says Heather
Anderson, an attorney representing VCPC. "Unfortunately,
[the] judge denied our request for the preliminary injunction
pending a trial on the merits of the case." VCPC and
the individual plaintiffs in the case have appealed the denial
of the injunction to the U.S. Court of Appeals for the Tenth
Circuit and are awaiting a decision.
Construction on the project began a month late, as did the
design work, which took five months longer than anticipated
because of the need for each community to approve their portion
of the project. The original completion date of Feb. 22, 2005,
has been extended to June 2005 and the project carries $10,000-a-day
liquidated damages for late completion.
According to NMDOT, the U.S. 70 widening has $2.2 million
in change orders-2.2% of the original contract price. "We
spent the first season of work getting through the design
process," Smith says. "We still accomplished a lot,
but not as much as we would have liked."
The asphalt highway is being widened from 35 ft to 75 ft,
mostly within the existing 690-acre right-of-way. The state
acquired less than 100 acres of land for $1.5 million for
the project, mostly in small slivers along the 38-mile stretch,
says Louie Pacheco, NMDOT's project development engineer.
 |
 |
|
The Hondo Valley
demonstration project winds through sensitive cultural
and historic locations.
|
Squeezing four lanes into two lanes of space meant carving
out a hillside with 340,000 lb of explosives. Over 1.7 million
cu yd of dirt and rock will be excavated and embanked on the
project. There are 450,000 sq ft of retaining walls, including
70,000 sq ft of soldier pile lagging walls, 60,000 sq ft of
gabion basket walls and 320,000 sq ft of soil slopes reinforced
with a geotextile fabric. "Supporting the down-slope
side of the roadway where there is not sufficient right-of-way
to allow the embankment slopes to spill out was especially
challenging to the design team," says Jim Jewell, Sierra
Blanca's deputy project manager. "We developed a series
of retaining structures that could be built from the highway
side of the structure to support the roadway embankment."
 |
 |
|
Precast and cast-in-place
structures were critical.
|
The job entails replacing storm drainage, including 6,000
linear ft of cast-in-place box culvert up to 6 ft by 8 ft,
and 45,000 ft of drainage pipe from 18 in. to 72 in. in diameter.
Five bridges will be replaced and a sixth widened. Consisting
of precast concrete girders and cast-in-place decks, abutments
and pile foundations, the bridges include four three-span
and two single-span structures. The largest bridge is 50 ft
high with a 200-ft-long span.
Currently, the project design has been completed and construction
is 56% finished with 44% of the contract time expended. Sierra
Blanca is making steady progress and expects to easily meet
its June 2005 deadline.
Even though the highway widening has not yet been completed,
the project already appears to be producing the desired safety
results. In July 2003, NMDOT designated the U.S. 70 project
as a "safety corridor" and placed a stronger emphasis
on reducing traffic accidents and deaths by increasing motorist
awareness. "In 2002 there were 12 fatalities along the
U.S. 70 Hondo Valley corridor," says Gary Shubert, NMDOT's
District II engineer. "In the year since breaking ground,
there has not been a fatality, which is an excellent improvement."
The author is a Las Vegas-based correspondent
for The McGraw-Hill Cos. He regularly reports on
design and construction industry issues.
All photos by Gill Kenny, courtesy of
Sierra Blanca Constructors.
Click
here for features archives >>
|