|
Rivals Crown State Capitol with New Dome
By Greg Lewicki
It took close to 90 years, but
Oklahoma finally completed its state capitol dome in the fall
of 2002-95 years after the state entered the union. According
to all involved, the use of design-build was crucial to the
success of the project.
"The design-build process was the only legitimate way
to have approached it," says John Jamison, project executive
for Manhattan Construction Co., Oklahoma City, one of the
joint venture contractors. "Putting a dome on top of
an existing building that is 87 years old...while keeping
the legislature in session [posed] severe challenges that
you couldn't depict on the normal" construction management
or bid documents. "There were too many unknowns,"
he says.
|
The original capitol architect, Solomon Layton, completed
the design in 1914 and construction began that year. However,
the state decided to deviate from the original design and
top off the capitol building with a low, 2-million-lb "saucer"
dome because the U.S. was on the verge of entering World War
I, the state was short of money and steel and other construction
materials were in short supply. There were rumblings over
the ensuing years to finish the job, but it was not until
1994, when Frank Keating (R) was elected governor, that momentum
turned in the dome's favor. Keating made it a priority to
find funding and complete the dome by Statehood Day on Nov.
16, 2002. Of the project's nearly $21-million price tag, all
but $1.3 million came from non-tax revenue, including $17
million that was raised through private donations.
Frankfurt-Short-Bruza Associates P.C. (FSB), Oklahoma City,
completed a feasibility study for the project in 1998 that
determined that the existing structure could support the 5-
million-lb, 157-ft-high x 80-ft-dia dome. Once the feasibility
study was completed, the Oklahoma legislature, through a special
act, allowed the project to go forward using design-build.
It was the first design-build project authorized by the state.
FSB provided architecture and engineering services and two
of the state's oldest construction companies, Flintco Inc.
and Manhattan Construction, entered into a joint venture as
Capitol Dome Builders, Oklahoma City. It was unanimously selected
by the state in 2000.
 |
 |
|
The capitol dome
project had lots of public scrutiny.
|
Although the two contractors were used to bidding against
one another, the visibility and importance of the project
compelled them to put aside their differences and work together.
"We are two archrivals. Both of our companies have been
in business close to a hundred years and we are the two largest
contractors in the state of Oklahoma," says Mark Grimes,
senior vice president of Flintco, Oklahoma City. "We've
always competed fiercely with each other [but] we had to put
our competitiveness aside and just do a good job because it
was such an important, visible project."
From the start, the team had an organizational advantage
with design-build project delivery. "I think what the
design-build approach afforded this project was the marrying
of the expertise of the design profession of architects and
engineers and the construction expertise of the contractor
at the very beginning of the project," says Fred Schmidt,
FSB director of architecture. "We really had to solve
together how we could accomplish not just the final design
but how we would actually get there from the first day to
the last day of construction."
"Extremely intricate constructibility issues were probably
what led this to design-build," says Jamison. "People
just had to sit down and scratch their heads and figure out
the rotation and the methodology of keeping this thing alive.
It couldn't have been done by any other method. Design-build
was such a very, very important player in a project like this
that had so many intricate things to discuss and feel through.
It's not a cookie cutter; you don't just put it on the ground."
The dome also was a highly visible project that needed to
withstand the test of time, be done right and serve as a beacon
for Oklahomans. "This was to be a 100-year-design type
of building, not a 50- or 25-year-life building," says
Schmidt. Oklahoma "wanted this to meet some very high
quality standards of construction. It had a very aggressive
timeline in terms of beginning of construction through completion
and I think those two elements together were probably the
leading reasons for the choice of design-build on this project."
"I would have hated to go into that project with a competitive,
low-bid process because it was an extremely difficult [project],"
says Dave Brown, construction administrator for the Oklahoma
Dept. of Central Services, which handled the project for the
state. "The dome had to basically be redesigned from
the original drawings to fit modern materials technology and
the firms did an excellent job doing that....We just felt
design-build was the way to go." Brown is a licensed
architect and he worked closely with the team to make sure
that the project went smoothly.
Dome Home
 |
 |
|
Steel "wagon
wheel" supported scaffolding.
|
Although FSB had never before designed a classic dome, Schmidt
says the firm has experience in designing long-span structures,
especially engineering airplane hangars with long, column-free
spaces. The firm completed its design for the dome in 2001
using Layton's old drawings as a template. However, FSB incorporated
modern materials into its design, which cut the weight of
the structure from an estimated 14 million lb to 5 million
lb. A structural steel framework largely was responsible for
the reduction. It was designed for fast and easy placement
and a "wagon wheel" of additional steel provided
a temporary platform for interior and exterior scaffolding.
It later was removed through the windows of the dome.
The dome itself was constructed of precast concrete panels.
The team had to find the right recipe of colored sand, stone
and cement to produce panels that matched the limestone used
in the rest of the building. A series of hidden tracks, tie-off
points and removable panels were included in the design to
allow for easier maintenance. Mechanical systems were designed
to evacuate smoke in case of a building fire through the dome
at 50,000 cu ft per minute and to dehumidify the air at the
top of the dome to protect finishes.
 |
 |
|
Dome colors symbolize
state history.
|
One of the complexities of the project was removing the existing
saucer dome, which left a gaping 80-ft-dia hole above the
capitol rotunda. Since the capitol remained open during construction,
the design-build team had to figure out a way to seal the
opening without disturbing the workings of the state government.
The team did this by closing off the fourth-floor rotunda
area and soundproofing it. The rotunda then was filled with
scaffolding and a work deck was installed 15 to 20 ft below
the saucer dome.
During the demolition, a 6-ft-high interior plaster cornice,
7-ft-wide plaster state seal and a 28-ft-wide stained-glass
skylight had to be disassembled and stored. Four historic
and priceless murals painted by artist Charles Bank Wilson
in the 1970s also had to be protected from debris and humidity.
Since the 8-ft-high by 25-ft-wide acrylic-on-canvas murals
were too large to be moved, they were protected with airtight
plywood boxes in which temperature- and humidity-controlled
air was pumped in from the building's ventilation system.
Humidity was monitored weekly.
Another challenge was the height and breadth of the dome
itself. The design-build team determined that a tower crane
would be the only possible solution for hoisting precast concrete
panels in excess of 15,500 lb and placing them approximately
200 ft from the tower base. The team erected the tallest free-standing
tower crane ever used in Oklahoma, with a final height of
281 ft and a boom length of 230 ft.
"That was another constructibility issue," says
Jamison. "How were we going to lift these big panels
and demolish and take everything up and out, instead of down?
It took a lot of teamwork."
Although the construction work went relatively smoothly,
the team members could not control Mother Nature and there
were some weather-related delays. "A big problem we had
building the dome was the wind," says Jamison. "We
were shut down 45 working days because of the wind. You have
25 to 30-mph winds [and] the amplitude goes up at 280 ft.
We were experiencing wind factors up to 50 mph, and we had
to shut down operations [because] we could not use the tower
crane." Despite these frequent shutdowns, the project
was not irreparably delayed.
The scaffolding also provided challenges. The entire exterior
of the dome was encased in scaffolding during the erection
of the steel superstructure. The scaffolding then was removed
for erection of the precast concrete sections. It was replaced
in sections, following the panels up the side of the dome.
The scaffolding then was removed again.
On the interior of the dome, a freestanding, independent
scaffolding system extended from the fourth floor of the rotunda,
through two temporary work platforms and up to the interior
apex (oculus) of the dome. This 140 ft of scaffolding was
self-supporting and not tied to the structure at any point.
Despite the various obstacles and challenges, all involved
agree that the project went off practically without a hitch.
"I don't think it could have gone any better," says
Grimes. "If we had done it 10 times over, I don't think
it would have gone any better than the first time. There was
a lot of good planning and a lot of good people on the project
who knew what they were doing, [which] made a really difficult
job go pretty smoothly."
A significant part of the design of the dome is its artwork,
which is meant to reflect Oklahoma's heritage, particularly
Native American. The state wildflower, the Gaillardia, or
Indian Blanket, is the central theme for the colors of the
dome's interior. A lower drum of blue symbolizes the vastness
of the Oklahoma sky, and is accented with bands of gold punctuated
by dark reds, blues and greens, which are meant to depict
Native American beadery. At the apex of the outer dome stands
a 5,980-lb, 21-ft, 9-in. bronze statue of a Native American
called, "The Guardian." The artist is state Sen.
Enoch Kelly Haney.
For Oklahomans, the capitol dome project took on a special
resonance, especially since it was constructed in the aftermath
of the terrorist bombing of the Alfred A. Murrah federal building
in 1994. "It was a very special project, a once-in-a-lifetime
project," says Schmidt. "It was an opportunity to
be a part of Oklahoma history in the making and so everyone
just rallied and everyone had their A-team on the project...and
it went off without a hitch."
"We were extremely pleased with the process, everything
seemed to work extremely well," adds Brown. "We
were real happy with the coordination and how well [the design-build
team] worked with the state."
Brown says that Oklahoma officials will continue to use design-build
if a particular project calls for it. "Design-build for
government agencies is coming alive now because what they
found out [with the Oklahoma state capitol dome] is they want
one-point responsibility, somebody that says 'I will design
it, I will build it and I will guarantee the money,'"
says Manhattan's Jamison.
The author, a freelance writer
and editor, lives in Weehawken, N.J. He has written articles
for Engineering News-Record, which he also proofreads.
All photos courtesy of Oklahoma State
Capitol Dome.
Click
here for features archives >>
|