|
Bold Thinking Wins Big U.K. Office Project
By Peter Reina
 |
 |
|
Photo
by Yves Chanoit
|
Demolishing three vacant office
towers turned out to be the key element in delivering a massive
$560-million design-build-finance-maintain project now being
built for the U.K.s Ministry of the Interior. The center
London project removes a public eyesore while providing new
office space for 3,000 workers.
Contractor influence over the new headquarters of the British
interior ministry, known as the Home Office, has been very
extensive because the builders also were largely responsible
for delivering the original concept. As a result, an unobtrusive
cluster of buildings on Marsham Street now is emerging from
the site where, for nearly 40 years, three harsh, 20-story,
slab-shaped towers rose, which critics said blighted a desirable
cityscape.
Designed by architect Terry Farrell & Partners (TFP),
London, the new $310-million Home Office development stretches
for about 200 m in a generally low-rise area close to historic
Westminster Abbey and the Houses of Parliament. In bulk and
height the new towers are more sympathetic to mixed-aged neighboring
offices and apartment buildings than its predecessors.
The three buildings will house civil servants now dispersed
but centered at Queen Annes Gate, a 10-minute walk away.
Built around spacious atria, the roughly equal size buildings
together will provide nearly 54,000 sq m of space on eight
levels, including two below ground. They will be integrated
by two sets of stacked, enclosed footbridges forming "streets"
along the developments length.
The Home Office agreement requires London-based Annes
Gate Property plc (AGP) to finance, design and build the project
in 34 months, ending early next year. AGP also will control
maintenance for another 26 years for roughly $250 million
at todays prices.
Paris-based Bouygues Group is a minority shareholder in AGP
but its U.K. construction division is fully responsible for
the design-build element. Its London-based affiliate, Ecovert
FM Ltd., will handle long-term operation of the buildings
and maintenance. AGP is 80% owned by the large U.K.-based
bank HSBC plc, which financed the project.
 |
 |
| Footbridges link
buildings by forming 200-m-long internal "streets"
throughout the project. |
Procurement of the buildings began just over seven years
ago when the Home Office invited negotiations with contractors.
The original plan was to refurbish the existing headquarters
in Queen Annes Gate. Bidders submitted their final offers
in late 1998, but the procurement was stalled by AGPs
audacious alternative plan. Instead of working with the existing
building, AGP urged the government to relocate to the Marsham
Street site.
Too costly to restore, the towers had been abandoned by government
departments. As empty eyesores, the towers removal appealed
to the government, which accepted AGPs proposal. But
for fairness, the Home Office gave other consortia the chance
to bid on the option.
AGP had an advantage over rival bidders because its architect
had studied alternative uses of the unwanted towers a few
years earlier, says Giles Martin, TFPs project design
director. Still in March 2000, AGP began a tough competition
against a single rival, emerging victorious four months later,
says Jean-Marc Arlot, Bouygues U.K.s deputy managing
director.
A long period then followed while AGP and officials negotiated
details of the contract and obtained outline zoning and building
permits. At the same time, HSBC, supported by Bouygues, assembled
the financing. All of the various strands came together in
March 2002 when contracts covering all aspects of the deal
were finally signed.
During bidding, a commercial team at Bouygues Paris
base had taken the buildings design far enough to establish
robust prices. Meanwhile, "the Home Office had its own
team of architects working with [the contractors] to ensure
we got a sensible standard," says Chris Rust-DEye,
the ministrys senior project manager. As a government
office, the design standard had to be good, but not lavish.
"You dont have marble floors, [but] you have stone,"
he says.
With contracts signed, the design team center moved to London
and a second Bouygues team emerged simultaneously to manage
construction. "The key people in the construction team
have been in my organization from day one," says Juan-Carlos
Pinedo, the contractors design manager. Led by Pinedo,
the design team includes TFP, supported by specialist firms.
Pell Frischmann & Partners, which had been co-developer
at the start, handled structural design. Electrical and mechanical
designs are by the London-offices of Flack & Kurtz and
Battle McCarthy Consulting Engineers & Landscape Architects.
And the facilities manager, Ecovert, has been "more than
a contributor" in the design development, says Bouygues
Arlot."They have a strong voice...about the whole-life
costs. Its about optimizing the design. Facilities management
is a key element in the process," he says.
 |
 |
| New Home Office
facility takes shape in neighborhood that includes Westminister
Abbey and Parliament. |
Bouygues also strove to include ideas from prospective subcontractors.
"We developed the designs for two or three months after
[contract signing]," says Pinedo. "Then, subcontractors
were appointed and we developed the design [further] with
their input and prices were adjusted accordingly," he
says.
One of those subcontractors was Shepherd Engineering Services
Ltd., Windsor, which handled mechanical and electrical installations.
"We had the opportunity to influence what was going into
the working drawings, certainly to the benefit of the program,"
says TFP operations manager Mark King. "It wasnt
only us in Bouygues office, but all the major subs."
Among the ideas adopted in the value-engineering phase was
modular wiring. Though more expensive to buy, the wiring arrived
precut to length with plugs attached. "It really has
saved time and reduced the work force we need on site,"
says King. Another innovation was the use of flexible hoses
to ceiling-mounted fire sprinklers, he adds.
 |
 |
| Facade design changes cost nearly
$2 million. |
While the construction team refined designs, the Home Office
continued tweaking plans as user needs became better understood,
says Rust-DEye. Bouygues Pinedo counts over 100
design changes after the contract was signed. Last summer,
"we said that if we wanted to complete on time, we needed
to put a stop to further changes," says Pinedo. "All
the changes have been managed jointly to ensure the budget
and program will be met."
Modifications to the facade costing nearly $2 million were
among the most visible owner-driven changes. In the planning
approval process, the original scheme failed to impress the
Commission for Architecture and the Built Environment, which
is funded by the government to promote good building design.
The architecture had been "pared down" says TFPs
Martin. "What was really missing was the joy that comes
from a big public building." Terry Farrells solution
was to recruit London and New York City-based modern artist
Liam Gillick to work with the facades.
One of Gillicks ideas was to have huge letters etched
into dark, opaque panels between the facade bays. He also
added a colorful, roof-level canopy along the main elevation.
Gillick "has taken the whole facade along 200 m and treated
it as a single entity," says Martin.
Numerous internal changes also emerged. For example, extra
money was spent on the main "street" running through
the three buildings via footbridges. More wood finishes and
brighter colors are being installed to make the 200-m-long
thoroughfare potentially less oppressive, notes Martin. And
cheerful egg-shaped pods replace more austere rectangular
meeting rooms.
There have also been more utilitarian enhancements. Raising
the buildings defenses "came as a result of 9/11,"
says Pinedo. Security improvements include the addition of
search bays at the vehicle entrances and of bollards around
the developments perimeter to halt rushing trucks, he
says.
Formidable Footprint
After site work began, "the only problem we had was
with demolition," says Jean-Pierre Bousquet, Bouygues
project director. The old buildings contained two World War
Two bunkers with 5-m-thick concrete walls that defied mechanical
destruction. The team was forced to weaken the concrete with
blasting. The $20-million demolition contract started in April
2002 and lasted three months longer than the 14 months originally
allotted, says Bousquet.
Construction finally began early last year in the 4-to-5-m-deep
pit, with Bouygues retaining the original walls and base slab
below ground. The new structures are detached from the old
concrete with drains in the intervening voids to catch any
water leaks. Rising out of the pit, the buildings are framed
in reinforced concrete, with cast-in-place walls and columns
and precast beams and slabs. The main elevations are clad
with curtain walls, while more economical windows penetrate
perimeter concrete walls in less obvious areas.
Unusual for the U.K., the fully air-conditioned buildings
will use heat pumps on all floors to extract and reuse heat,
says Neil Pixsley, Bouygues senior manager for electrical
and mechanical system. "From an energy point of view,
you cut down on your chillers," he says. To ensure that
key structural workers were familiar with Bouygues methods,
the firm imported about 260 of its regular operatives from
France. The firm relies heavily on precast concrete for slabs
and beams and uses steel rather than timber-faced formwork,
says Bousquet. When it came to buying precast concrete, he
was surprised to find a Belgian supplier underbidding local
rivals.
Structural work now is done and the focus is on cladding
and internal work. Having started its $36-million electrical
and mechanical installation contract last September, Shepherd
Engineering is on course to handing over the project this
November. With most construction uncertainties now eliminated,
Rust-DEye estimates the extra cost of all the change
orders at about $18 million, which he believes is modest for
a project of this size.
The procurement approach used on the Home Office project
transfers more of the risks to the contractors than simple
design-build, says Rust-DEye. While the owner is charged
with securing zoning permission, for example, the contractor
must negotiate all of the resulting details. And while on
design-build, "you have quite an integrated approach
in terms of design development, here, the risk stays with
AGP," he says.
The author lives in London. He is ENRs
long-time European correspondent. He also regularly writes
the In The News pages of DesignBuild Magazine.
All photos by Peter Reina for Design
Build
Click
here for features archives >>
|