|
Bridge Steps Lightly To Spare Cash Crop
By Elaine S.
Silver
The Florida panhandle area near the Bryant Patton Bridge
is known for its natural beauty and economically important
oyster beds. To replace the aging 4-mile-long structure, a
first-time design-builder signed on for a $72-million lump-sum
contract and threw in a 10-year abutment-to-abutment warranty
for good measure.
Located on the Apalachicola Bay in the northeast portion
of the Gulf of Mexico, the original Bryant Patton Bridge tied
the town of Eastpoint and State Routes 98 and 319 to St. George
Island in 1965. The two-lane bridge needed to be replaced
because corrosive salt water and the heavy wave action of
the bay damaged substructure elements. In addition, inadequate
lane widths on the bridge caused significant traffic back-ups
and the lack of shoulders raised safety concerns.
In keeping with its lush surroundings, the causeway portion
of the bridge also had become a nesting ground for several
species of protected birds. The old bridge replaced ferry
service to the 29-mile-long island, which has 700 year-round
residents and is an attractive summer tourist destination
with many rental and vacation homes.
The new bridge is comprised of two parts. The low portion
causeway is 3 miles long, mostly on the north or mainland
side, with minimum clearance of 14 ft above the water. The
high or channel part has 65 ft of vertical clearance from
the water. The new prestressed concrete bridge, containing
two lanes and two breakdown lanes, was completed in May for
the Florida Dept. of Transportation by the design-build team
of New Orleans-based Boh Bros. Construction Co. LLC and Jacobs
Civil Inc., Tampa.
After hearing about a feasibility study, the team started
work on the project in 1997a year before it was even
announcedin order to increase its chances of submitting
a winning proposal. Once awarded the job in April 1999, the
design-build team completed the project in 1,547 calendar
days.
Collaboration between designer and contractor guided the
entire project. "The beauty of design-build is that the
engineer gets to design towards the strength of a particular
contractor," says Steve Zendegui, Jacobs senior
bridge engineer. In this case, that meant Boh Bros.
The contractor got the project rolling by suggesting that
the team use an unusually sized 54-in.-dia pile to satisfy
FDOT structural and environmental concerns. The piles, fabricated
in 16-ft-long sections, have a 38-in.-dia hollow core and
8-in.-thick walls with holes for steel tendons that are prestressed
and grouted. The piles were driven into silt and sand to a
lime rock bearing strata. The larger size minimizes disturbances
to the bay bottom. The piles support a cap, piers and the
roadway. "The overall selection of the pile [size was
made] because of the oyster beds," says Ed Scheuermann,
Boh Bros. office project manager.
 |
 |
| Old and new bridge
structures were built near important oyster beds. |
The Apalachicola Bay is an aquatic preserve and home to the
countys largest oyster-producing area, a major economic
force in the local economy, so the new bridge had to be built
with minimum impact on the 10,600 acres of oyster beds. "Oyster
harvesting is the largest industry in the area," says
Cindy Collins, assistant at the Apalachicola Chamber of Commerce.
"Tourism comes in a close second, but Apalachicola Bay
produces 90% of Floridas oysters." According to
Mark Berrigan, bureau chief with the division of Aquaculture,
Florida Dept. of Agriculture and Consumer Services, oysters
bring in "about $20 million to the area."
In order to ensure that the bridge would pass muster from
the permitting agencies, "we latched onto using these
large piles because Boh had used them before and we also had
to design a portion to resist possible barge impact,"
says Zendegui. "This enabled us to significantly reduce
the number of piles used." If a standard 30- in. pile
been used, 42 would have been needed in the main channel instead
of 15 of the larger piles. "This is a huge savings,"
says Zendegui. "There are fewer piles so there is less
impact on the environment and it was much less time- consuming
to drive 15 piles as opposed to 42."
The bridge sits on a total of 650 piles, mostly three per
bent, and they range in length from 70 ft to 96 ft, with about
10 ft of each pile visible on the lower approaches. To protect
the oysters, the design-build team hired local fishermen to
relocate the beds directly under the piles.
Using post-tensioned precast concrete piles speeded the work
while the team completed a geotechnical survey of soil conditions.
"We could start making pieces immediately and then we
could say we need a certain length of pile at a particular
bent. So when we got the geotechnical data, the fabricator
could join the pile segments together for the appropriate
length for each of the substructure components," says
Zendegui. "This saved several months at least."
Building the bridge put Boh Bros. at risk. Before settling
on the larger pile design, the contractor did a test run.
"We cast a sample pile and drove it into a similar-type
soil bed in Louisiana," says Al Flettrich, Boh Bros.
senior project manager, heavy construction. "That way,
we could present our findings to FDOT and we knew for ourselves
that the pile worked well and we could install it under the
specific soil conditions."
Not knowing specific soil conditions also was a risk because
FDOT provided data on only 12 borings in the request for technical
proposals. The team ended up making over 100 test borings
during the project. Fortunately, the soil turned out to be
fairly uniform. "In design-bid-build, the piles are unit
price and in a lump-sum job, the risk was ours, not knowing
what the pile length was going to be" says Flettrich.
"One of the other bidders dropped out because of this."
 |
 |
 |
 |
| Precast, post -tensioned
concrete sections saved time and money. |
The design-build team also took a risk in obtaining all of
the necessary permits for the job as it surged ahead. If FDOT
builds a job using design-bid-build, it has to obtain all
the permits even before the job can be let out to bid, says
Doug Cox, Jacobs southeast region director of construction.
"In contrast, we could submit the plans in pieces to
get a jump on the project." The bridge roadway just needed
an Environmental Resource Permit, so it made sense to begin
with that, says Cox. "Using the design-build contract
vehicle means that we can start and complete a bridge in four
to five years instead of 10 years," says Steve Benak,
construction and materials engineer for FDOTs District
3.
But one advantage to having permit responsibility was the
ability to work directly with utility companies. "This
is essential under design-build," says Cox. "We
can pay [the utilities] premium time to get the relocation
job done or we can elect to have the contractor do it and
then you can get it out of the way. If we pay the utility
company $30,000 in overtime, we can save $100,000 in time.
We are always evaluating as a team how we can add extra value
to save the job time and money."
After one verbal agreement, the team ran into a bureaucratic
glitch over permits to build compensatory treatment drainage
ponds for the stormwater runoff from the bridge roadway. The
Florida Dept. of Environmental Protection decided the plan
was inadequate because it required relocating an existing
sewer line.
"The design-build team had to change the plan for the
runoff at its own cost, find a solution and go through the
permitting process," says John Kemp, senior project engineer,
Parsons Brinckerhoff Construction Services, Eastpoint, which
was hired by FDOT for project construction, engineering and
inspection. The team then found an alternative site at a special
inlet to treat the runoff water. "In the end, everyone
benefited," Flettrich says.
 |
 |
|
Special grout preserves integrity
of steel tendons in concrete piles.
|
"The largest issue happened when we changed the grout.
We wanted it to happen and we paid for it," says FDOTs
Benak. FDOT changed its grouting specifications in mid-project
from cement to expensive thixotropic grout. The grout is used
to secure the post-tensioned cables in the piles and Scheuermann
says the team was a little uncomfortable about using the new
grout. "We were using a 54- in. pile that has a pretty
good history and then FDOT wanted changes made. But when you
are sitting there with the warranty, it is hard to accept
them."
Each change potentially could alter the long-term maintenance
needs of the bridge, which remains the design-build teams
responsibility. FDOT paid for the change and Boh Bros. sent
some of its engineers to a special course to learn to use
the new grout.
FDOT wanted the grout change due to bitter experience
on two other Florida concrete bridges. The internal post-tensioning
strands were breaking on relatively new structures because
the old grout would separate and allow salt water to bleed
in, creating a corrosive environment. Thixotropic grout stays
homogenous and eliminates voids while providing corrosion
protection. "The important thing is that it all worked
out," says Scheuermann.
The teams 10-year abutment-to-abutment warranty played
a role in design and materials choices. "By providing
the warranty, we had to ensure that we had the best materials.
We designed some things differently to make sure they exceeded
the standards," says Flettrich. "For example, where
specifications called for four anchor bolts, the team put
in eight."
The bridge now is open and the old one is being dismantled,
although a section will remain as a bird-nesting sanctuary.
Satisfied with their experience at St George Island, the team
now is partnering on a new Interstate 75 bridge over the Peace
River. "Using design-build is a lot more fun. The whole
process allows the contractor to interact from the beginning
to use our best methods and resources to construct a better
product with a better price in a shorter time," says
Flettrich. "Id like to see design-build come to
Louisiana and Alabama."
The
author, a freelance writer, lives in the Hudson River Valley
of New York State and reports frequently for Design•Build
and other publications.
All photos courtesy of BOH BROS.
Click
here for features archives >>
|