|
Nevada Green Building Breaks State Barriers
By Tony Illia
After an initial bumpy ride over
bridging and adjusting to new teaming relationships, the State
of Nevada has comfortably settled into the drivers seat
to deliver its first public design-build projecta new
community college telecommunications building in North Las
Vegas. The project could open the door to more extensive use
of the integrated delivery system due to pent-up demand and
persistent problems with traditional bidding.
While the state Legislature approved
design-build for public works in 1999, it was never used because
there was a $30-million threshold. We dont have
many projects $30 million or more, so the law was revised
in 2001, says Gus Munez, deputy manager for the Nevada
State Public Works Board. Design-build is another procurement
tool and there was a strong desire to use it. Under
the revised statute, new buildings estimated to cost between
$500,000 and $30 million now qualify for design-build. But
it still took a series of high-profile project miscues and
an increasing demand for faster delivery time to force the
state to put design-build into play.
Southern Nevadas population
grew by 200,776 people between April 1, 2000, and July 1,
2003, or an average of 5,019 new residents per month, according
to the U.S. Census Bureau. Public officials have been under
mounting pressure to deliver buildings quicker to keep pace
with this growth. But problems with traditional design-bid-build
delivery on recent projects has generated sharp criticism
and increased scrutiny.
The problem projects include the
five-story, 301,000-sq-ft Lied Library at the University of
Nevada, Las Vegas, which opened 15 months late and 30% over
budget. Completed in January 2001, the library project underwent
an independent audit and a three-year construction defect
dispute. After spending over $1-million for legal fees and
experts, the state last June paid a $1.7-million settlement
to general contractor Tibesar Construction Co. Inc., Las Vegas,
to avoid a trial. Similarly, the 188-bed Veterans Affairs
Nursing Home in Boulder City opened a year late in 2001 after
the state replaced its general contractor, Addison Inc., Las
Vegas, and hired another to finish the work.
Design-build was granted its trial
run in 2003 on the Morse Arberry Jr. Telecommunication Building
at the Community College of Southern Nevada (CCSN), Cheyenne
campus. Named after the state assemblyman who helped secure
its funding, the new building is an energy-efficient, high-technology
structure that enables the fast-growing college to serve another
500 students. The telecommunication building opened on time
Aug. 30.
Space is critical. CCSN currently
turns away 17,000 students per semester due to space constraints.
In the 1990s, CCSNs full-time enrollment grew 182%,
jumping from 5,402 to 15,214 students. And enrollment is expected
to reach 21,436 students by 2007. That would make CCSN the
states second-most-attended higher-learning institution
after the University of Nevada, Las Vegas.
Las Vegas-based Martin-Harris Construction,
along with design subcontractor JMA Architecture Studios,
won the projects two-stage state-sponsored design-build
competition on June 23, 2003. But the process was arduous.
Making
Connections
The state Public Works Board hired
Swisher & Hall Ltd., Las Vegas, in Oct. 2002 to produce
bridging documents. Swisher & Hall had done the seven-phase
master plan for the 80-acre, 30-year old CCSN Cheyenne campus.
While bridging documents often include minimum design, these
documents included 90% complete schematics with system performance
specifications.
The use of bridging documents is
controversial. Critics charge that it is an unnecessary expense,
diluting any realized cost savings from the design-build process.
They say referencing the state public works code should be
sufficient, rather than designing the building twice. But
supporters feel that the practice ensures a level playing
field, making certain that the owner receives the best value.
Without bridging documents, design-build teams could
cut corners using lesser performing systems to show a cost
savings, says Bob Gilbert, CCSNs director of site
planning and construction management.
Request-for-proposals were solicited
in Feb. 2003, with nine prequalified teams offering everything
from steel-framed to masonry-block buildings. After reviewing
schedules, descriptions and estimates, the list was whittled
down to five teams, with losers each receiving a $25,000 stipend.
That $100,000 expense raised a few eyebrows, with some skeptics
saying it attracted firms looking for a quick payday with
no intention of securing the work. Others insist $25,000 was
not nearly enough to defray costs. Some competitors
had nearly $200,000 into their schemes, says Michael
Crowe, JMAs senior project manager.
Martin-Harris and JMAs concrete
tilt-wall building proposal, which increased the building
size from 84,500-sq-ft to 92,000-sq-ft, prevailed. Although
larger, it was still cost-effective due to some innovative
value engineering. For example, Martin-Harris shaved $400,000
from the total by using a special adhesive for application
of the limestone veneer, as opposed to a mechanically fastened
system.
The state Public Works Board is
required to use price as 30% of its determining criteria for
a project award. The two-story structure had an aggressive
18-month design-to-completion schedule that was compressed
to 14 months after slow initial document development and a
lengthy state approval process. A normal design-bid-build
process for a similar building would have taken the state
36 months to complete. This was the first time we had
done this. So the documents needed to be developed and approved
by the state Attorney General, the Finance Board and Public
Works Board, says Munez. As a result, Martin-Harris
pre-ordered critical-path items like steel and began site
work while still developing plans. The contractor eventually
would have up to 225 tradesmen on site during the height of
construction. Adopting a strategy to build as drawings were
approved enabled Martin-Harris to fast-track work. The
state Public Works Board was very accommodating, providing
plan turnarounds within two and a half weeks, Gilbert
says. In the past, its taken up to nine months
to get plans approved.
Contract incentives and penalties
also accelerated the projects breakneck schedule. Martin-Harris
signed a guaranteed maximum price contract for $15.8-million.
If it came in under that amount, the money would be divided
70:30 between the state and the contractor. Hired by Martin-Harris,
JMA was paid a flat fee for design services. The project finished
about $100,000 below its guaranteed maximum price, says Don
LaRue, Martin-Harriss project manager. Had it opened
late, the contractor would have faced $2,690 a day in liquidated
damages after Aug. 30.
There was some give-and-take during
the project that required adjustments between the owner and
its design-build team. The state was accustomed to interfacing
directly with the architect, a habit it relinquished reluctantly.
Under design-build, the person who holds the contract
is supposed to be the primary contact, says a project
official. But the state was used to having more contact
with the architect than contractor. In a design-build process,
the owner needs to give up part of that control. The design-build
contractor should control the architect and subcontractors
since they are the one at risk. But since this was the states
first design-build project, they were very cautious.
Hot
Wired
Situated on 4.75 acres, the new
building consists of 87 eight-in.-thick, cast-in-place concrete
panels. The largest panel measures 50-ft tall by 26-ft wide,
and weighs 130,000 lb. The building sits atop a slab foundation
with a continuous 30-in.-wide by 30-in.-deep spread footing
around its perimeter, plus two grade beams measuring 4 ft
wide by 30 in. deep. While the 47-ft tall building uses 1,000
tons of steel, its exterior panels provide most of the structural
support, enabling minimal sheer walls for interior flexibility.
With hundreds of miles of electrical conduit, the building
has a depressed floor panel system up to 12-in. deep that
allows power, fiber optics and T-1 lines to be easily moved
from room to room. The configuration also makes it easy to
adapt the building to new technology as it emerges and to
changing use requirements.
The concrete walls also muffle
sound from neighboring Nellis Air Force Base, the Home
of the Fighter Pilot. Since the college campus lies
under Nellis flight path, the walls dampen jet noise
for a quiet learning environment. The buildings roof
was engineered to support nearly 24 antennas and satellite
dishes, the largest of which measures 50 ft tall and weighs
6,000 lb. At 8 in. thick in some areas, the roof can withstand
live loads while refracting sound from overhead airplanes.
Although the state developed and
owns the building, the community college is responsible for
its operation and maintenance. And since the competition proposals
came in under budget, the state agreed to pursue a silver
LEED (Leadership in Energy and Environmental Design) certification
from the U.S. Green Buildings Council, Washington, D.C. This
is the first LEED-certified public building in the state.
While [LEED certification] costs about $500,000 more
upfront, the building will save up to 20% in operating expenses,
says Gilbert.
The LEED certification resulted
in about 25% of the building being constructed from recycled
materials, ranging from asphalt and carpet to doors and ceiling
tiles. It uses environmentally safe materials, such as particle
board made from compressed wheat and low volatile organic
compound glues, sealants and paints to cut emissions.
The building is serviced from a
4,000-sq-ft central plant with two high-efficient boilers
and chillers, reducing a duplication of systems for future
expansions. And 75% of the rooms are illuminated by direct
and diffuse daylight though the use of windows and light shelves.
The second floor uses 66 sky-tubes or 21-in.-dia
parabolic lens roof openings that light interior areas. Each
room has electronic sensors that turn off lights when not
in use and there is low-ultraviolet glazing and exterior metal
sunscreens on the buildings western exposure to minimize
heating and cooling costs.
The telecommunication building
is connected to the colleges computer building by a
second-floor 60-ft-long steel canopied bridge supported by
four 16-in.-square steel columns. The span carries wiring
that ties the new building into the main campus security and
electrical framework. The college can monitor all of the telecommunication
buildings systems, enabling it to schedule classes during
the most energy efficient times of the day. It also aids in
troubleshooting problems early.
Housing a college staff of 65 teachers
and technicians, the building contains a 100-seat auditorium,
a 35-ft-high lobby/exhibit area, 29 classroom/labs, offices,
student lounges, media production and staff areas. The college
installed $9.5 million worth of new and used furniture, fixtures
and equipment, coordinating through Martin-Harris.
The new building now serves as
home to the engineering, computing/information and media technology
departments. It expands the colleges certification programs
in fiber optic communication, computer networking, high-speed
data transmission, satellite transmissions, wireless networks,
television broadcasting and digital media. CCSN already operates
one of the largest Cisco Networking Academy Training Centers
in the U.S. Our main concern is that its going
bolster our enrollment, says Warren Hioki, associate
dean of CCSNs Engineering Technology Dept.
The author
is a Las Vegas-based correspondent for The McGraw-Hill Cos.
He regularly reports on design and construction industry issues.
Photos by Tony Illia for Design Build
Click
here for features archives >>
|