|
Border Crossing Bridges Binational Differences
By Paul Rosta
A new building in the remote North American
prairie houses what may be some of the worlds best-traveled
workers. Every day, each one can make hundreds of international
trips and still be home for dinner.
Although this sounds suspiciously like
a top-secret experiment in futuristic transportation, the
truth is more prosaic. The building in question, which opened
in September, is the centerpiece of a $31.2-million shared
port of entry that straddles the U. S.-Canada border. To overcome
the intricacies of constructing a binational project, the
U.S. General Services Administration selected design-build
with bridging documents as the project delivery method.
With 100,000 sq ft of space distributed
among the main building and six ancillary structures, the
complex fills a critical function. Located at the northern
end of U.S. Interstate 15 between the tiny towns of Sweet
Grass, Mont., and Coutts, Alberta, the port is "the only
gateway for the prairie region," says Dane Ashlie, senior
project manager for the Canada Border Service Agencys
Real Property and Environmental Directorate.
 |
 |
| Big
Sky country's new border crossing successfully overcame
complex code, regularly and labor problems. |
With 1.3 million travelers and 413,000
shipments passing through it in 2003, the Sweet Grass-Coutts
station is the third-largest crossing in the western U.S.
and Canada. The new facility houses personnel from a host
of Canadian agenciesCanada Border Services Agency, Dept.
of Citizenship and Immigration and Canadian Food Inspection
Agency. U.S. agencies include Customs and Border Protection,
Immigration and Customs Enforcement, Dept. of Agriculture
and Food and Drug Administration.
When the two governments signed the Shared
Border Accord in 1996, both nations already had separate projects
in the pipeline for the Sweet Grass-Coutts crossing and several
other locations, says Jim Oberg, director of GSAs northern
border program. Then U.S. Customs officials "came to
us and said, We want to do a joint facility. What will
it take?" So the teams went back to the drawing
board. Owing to the change in direction and the complexities
of developing a binational project, "we lost a year,
and we picked it up by doing design-build," says J. Lach,
GSAs Portland, Ore.-based project manager.
GSA Chief Architect Ed Feiner recommended
design-build for Sweet Grass-Coutts because of the June 2000
success of the Lloyd D. George courthouse and federal building
project in Las Vegas. "This project lent itself to design-build
so well because it was a joint facility," Oberg says.
Because of the projects international nature, design-build
delivery would require the contractor, not the governments,
to "wrestle with and come up with [unique] solutions
for doing a joint facility," such as addressing labor
and materials issues, Oberg says. Design-build took the headaches
away from the owners and "placed the risk with the entity
that was best able to handle the risk," he adds.
Frontier First
Four agencies collaborated on funding:
GSA (48.2%), Canada Border Services (43.6%) and the Montana
and Alberta transportation departments (4.1% each). Under
the shared-border accord, the nations switch off taking the
lead on the projects and GSA took its turn with Sweet Grass-Coutts.
To prevent the competition from becoming prohibitively expensive
for contractors, GSA used a two-step selection process. The
agency first evaluated teams qualifications and experience,
but did not require the costly step of submitting a design
or a price. GSA then invited four teams to bid. The successful
team leader, Calgary-based Bird Management Ltd., came full
circle with its $25.9-million contract award. Half a century
earlier, the Canadian side of the crossing was one of the
first projects by the then-fledgling company. Bird subcontracted
design work to Edmonton-based Kasian Kennedy Architecture.
 |
 |
|
Bridging documents
laid out requirements for certain governmental areas
of the Sweet Grass-Coutts station.
|
The border stations specialized
requirements called for a hybrid delivery that combined design-build
for many key elements with prescriptive design for others.
As a result, "we were provided with quite a few guidelines,"
says Colin Fong, Birds project manager. Critical government
areas such as search, interview and detention rooms needed
virtually complete designs. "If we didnt specify
it in the design, we get what we get," Ashlie explains.
Thats why GSA went with bridging documents provided
by architects Tim Felchlin and Kate Diamond, of Los Angeles-based
Siegel Diamond Architects. They brought design to the 25%
to 35% level and specified much of the interior design, including
the building footprint, floor plan and room size.
With its skewed grids, multiple pitches
and barnlike elements, the main building, in particular, "was
a bit more of an architectural statement than your typical
design-build structure," says Duane Babiak, project engineer
for Calgary-based structural engineering consultant Read Jones
Christoffersen Ltd. "In all instances I can recall, we
were following the parameters that were laid out," Fong
says. "Certainly the agencies were very helpful in at
least identifying to us what we could and could not do."
 |
 |
|
Border was an invisible barrier
hurdled by use of native Canadians who could work
in U.S. under old treaty.
|
Design-build required contractor and
consultant input on other key elements, such as mechanical,
electrical and structural systems. That promoted flexibility.
"We had some leeway in terms of coming in with a better
mousetrap, so to speak," says Fong. The bridging approach
"certainly doesnt limit using our own value engineering
on this project." Probably the biggest and best modification
to the buildings was for the structural framing system. The
original design called for a composite concrete slab and steel
beams, which was modified to an open-web steel joist and slightly
thinner slab, says Babiak.
Design-build delivery also helped Sweet
Grass-Coutts achieve another distinction. It is the first
border station to win certification by the U.S. Green Building
Council as a LEED (Leadership Energy and Environmental Design)
project. During the five years of design and construction,
the team incorporated sustainable principles. Felchlin and
Diamonds bridging documents incorporated such criteria
as energy efficiency, environmentally sensitive materials,
waste management and water conservation.
"We didnt spec out how to
achieve LEED certification," says Lach. "We did
it entirely as a performance spec," leaving it up to
the design-build team to choose specific elements, he adds.
In response, Kasian Kennedys Ken Mah, Merve Weiss and
Andre Kroeger developed such sustainable features as exterior
finishes, ceiling tile with 90% recycled content and extensive
use of natural light.
Double Challenges
From the outset, the project team had
to deal with double stakeholders, paired sets of federal,
state and local agencies, plus double codes and regulations.
To underscore the complexities, Lach notes that his current
project, a federal building renovation in Portland, requires
12 to 15 signoffs for any major decision. The new port at
Sweet Grass-Coutts needed 80 approvals.
Administrative challenges also cropped
up in areas like managing accounts payable. Canadas
share of funding had to take a round trip. As lead agency,
GSA administered Canadas contributions, which were exchanged
from Canadian to U.S. dollars. Those funds then were transferred
back and exchanged back to Canadian dollars before reaching
subcontractors and suppliers on the northern side of the border.
"We had to figure out a way of doing this [because as
the currencies fluctuate], there can be a dramatic hit on
Canadas budget when they transfer that funding over
to us," Oberg says.
The ports shared main building
posed the greatest challenges. Planning had to take into account
different regulations. In cases of code differences, "it
had to be built to all of the applicable codes, whichever
was most stringent," Lach says. Canadian regulations
do not require a sprinkler system for a building of that size,
but sprinklers were installed to comply with U.S. fire codes,
says Ashlie.
| |
 |
|
Architectural statements abound
at new facility.
|
One seemingly small difference had far-reaching
implications. "Most of the sharing had to be on the U.S.
side because our inspectors can carry guns," Oberg says.
As a result, the shared locker room had to be on the U.S.
side in order to prevent gun-bearing U.S. personnel from violating
Canadian regulations. The border also presented labor and
materials issues. For example, the elevator shaft is located
in the U.S. but the mechanical room is in Canada. Lach notes
that there was no international zone that "would have
allowed materials and laborers to come in from both sides."
In parts of the building straddling the border, "we made
sure we were using only Canadian forces or U.S. forces right
up to that line," Fong says. "Once they get to the
border, they couldnt step over the line," Lach
adds.
"The labor force out here in the middle of nowhere is
a challenge in itself," says Henry Ong, the on-site owners
representative and construction manager for Abide International
Inc., Sonoma, Calif. One successful strategy was to hire Canadian
Indian workers, such as ironworkers and electricians. Unlike
native Americans, native Canadians may work on both sides
of the border under a 1794 treaty.
 |
 |
|
The most stringent U.S. or
Canadian code ruled.
|
Border-conscious building also was demanded at the 30-meter-long
pedestrian bridge that has exactly half of its 4.5-m width
in each nation. To comply with labor laws, the Calgary-based
subcontractor, Anglia Steel, fielded both U.S. and Canadian
crews. Each crew operated a crane to erect half of the prefabricated
steel bridge. Native Canadian ironworkers then welded the
steel sections together.
Subtle differences also surfaced in structural steel. Although
the codes of both countries are fairly close, structural drawings
in the U.S. typically display more detailed connection information
than they do in Canada, says Babiak from Read Jones Christoffersen
Ltd. In Canada, the steel fabricators consultant, rather
than the project structural engineer, often provide those
connections, Babiak explains. For the structural engineer,
the challenge was "presenting information in a form that
the industry on both sides of the border are used to seeing,"
he says. Since inspectors and other professional personnel
may work on both sides of the border, Calgary-based Canspec
provided field construction services for the entire project.
Design-build proved especially valuable "when we were
hit with a very significant impact in the middle of construction.
Design-build helped us not have a delay," Lach says.
Ong of Abide International adds: "Thats the beauty
of design-build. You can be reviewing the design submittals
for the structural [elements] while theyre putting the
footings and foundation in."
By Paul Rosta
The author is a correspondent for The McGraw-Hill Cos. He
lives in
New York City, where he regularly reports on construction
industry issues.
Photo credit: All photos by Timothy Hursley
|