|
Saving School System Takes Strong Teamwork
By Victoria L. Tanner

Take a client with multiple problems,
a complex fast-track simultaneous construction plan involving
more than 20 aging buildings, a make-or-break deadline and
an out-of-town contractor and mix them all together under
the watchful eyes of a small town school board and what do
you get? The word disaster might spring to mind, but the community
of South Bend, Ind., hopes it is a recipe for a major success
story.
The untried, the unusual and the unorthodox
all came together as the South Bend Community School Corp.
(SBCSC) banked on a new superintendentand design-buildto
jumpstart the school systems fortunes. When Joan Raymond
took over as the superintendent of SBCSC in 2000, she had
a proven track record. Having taught in or administered school
systems in major cities, Raymond had seen her share of tough
cases.
Although South Bend is a quintessential
midwestern small town, it shared many of the same problems
facing urban school systems. Poor student performance ratings,
truancy and discipline issues and a student exodus to alternative
educational options all reflected the school systems
difficulties. SBCSC also was struggling to meet the requirements
of a 1980 integration consent decree with the U.S. Dept. of
Justice and the U.S. District Court for the Northern District
of Indiana.
On top of that, Raymond also was taking
charge of crumbling infrastructure. Of 33 schools in SBCSCs
inventory, a majority were well past their expected service
life and could not support instructional programming needs.
And there also were money problems in the 21,000-student system.
But before she could even start, Raymond
had to clean up a floundering high school construction project
that she had inherited. The job was more than a year behind
schedule, severely over-budget and hopelessly entangled in
construction disputes. During her first week on the job, Raymond
called Mark Wight, owner of Wight & Co., a Darien, Ill.-based
firm that previously had worked on Illinois school projects
with Raymond. She asked him to send in a team to assess the
situation.
With 11 prime contracts, and no apparent
leader, "it was a real mess," says Ken Osmun, Wights
vice president of construction services. "Frankly, they
couldnt find another local construction manager that
would touch this project. That was our entry and everybody
knew we were nuts for even trying." Raymond hired Wight
to salvage the job and within six months the high school was
complete and Wight had cemented a solid relationship with
the school board.
Grappling with the SBCSCs larger
problems required equally assertive resolve and Raymond devised
a series of options for redistricting the school system. The
alphabetic attempts took different philosophical approaches
to the problemPlan A, Plan B and Plan Cbut ultimately
left South Bend littered with a string of unworkable ideas.
None of the plans could get the needed community support or
work within the limits of the school systems strained
budget. And whatever was done had to be approved by the federal
judge overseeing implementation of the consent decree.
In a town where the University of Notre
Dames "Touchdown Jesus" mural literally looms
over the landscape, maybe it was divine inspiration that finally
encouraged Raymond to step back into the pocket and throw
a "Hail Mary pass" she called Plan Z.
Heaven Sent
Plan Z completely rethought the school
system approach. Key components included a total grade level
reorganization of the school system; conversion of certain
schools to serve different grade levels; a new approach to
curriculum and academic instruction; development of special
gifted and talented activities; open enrollment through a
choice system; establishment of magnet schools at both the
primary and intermediate levels and development of specialized
"focus programs" at all four high schools. "It
was the last option," says Bob Farkas, a Wight senior
project manager. "And it was the most aggressive of her
proposals."
 |
|
|
OSMUM
|
The school board adopted Plan Z in December
2001 and Raymond won Justice Dept. approval in July 2002.
At its core was a $50.8-million construction program. Overall,
the work represented approximately 500,000 sq ft of renovation
and 110,000 sq ft of new construction throughout the system.
The bulk of the construction had to be completed before the
late-August start of the 2003-04 school year and most work
could not start until the summer recess began in June 2003.
Work on some of the more significant additions would continue
through the 2003 school year, requiring phased construction
as students were moved in and out of temporary classroom facilities
during the process.
With the construction component of Plan
Z critical to the overall effortand still stinging from
its last major construction projectSBCSC was determined
to find ways to maintain oversight and ensure tighter controls.
While Raymond was battling to win approval for her plans,
she received a letter from John H. Strauss, an experienced
professional working in the area. "She was really getting
beaten up in the press and I sent her a letter saying that
I thought I could help. She called me and asked me to come
and see her," Strauss says. A career Naval officer and
Annapolis graduate, Strauss had managed all types of Naval
facilities and gone on to a post-naval career that gave him
further exposure to managing hospitals and major institutional
buildings.
 |
 |
| LaSalle Academy, created from
the bones of an aging high school, is a new magnet school
for science. |
In short order, Raymond brought Strauss
on board as assistant superintendent for facilities management.
The seasoned professional would anchor a formidable management
team for tackling Plan Z. Impressed with Wights work
on the high school bailout, the firm was listed as a potential
contractorbut not the only one. Wight urged Strauss
to award the project on a design-build basis, arguing that
design-build was the only viable solution because of the compressed
schedule, multiple sites and intense coordination that would
be required.
Considering the options and alternatives,
Strauss also became convinced design-build could work. "We
had to do some legal research to ensure we were within our
rights to accomplish the design-build work," Strauss
says. It would be a first for SBCSC and for Strauss so the
concept was tweaked to suit the school boards specific
interests and give members a comfort level about the untested
method. After negotiations that Osmun describes as "tough
and long," SBCSC and Wight came to terms on a hybrid
design-build effort that was unique in many ways.
While Wight would lead the design-build
team under a construction management contract, SBCSC insisted
on awarding all contracts directly. Wight was given the design
and construction lead on five of the six major projects, but
Strauss and SBCSC negotiated a "shotgun marriage"
with an established local architectural-engineering firm,
DLZ Indiana LLC, which had a long track record on SBCSC projects.
DLZ, working on its first design-build program, was tapped
to handle site, civil, structural and mechanical-electrical-plumbing
design work on all six major projects, as well as taking the
architectural lead on Kennedy Primary Center. SBCSC insisted
on awarding and administering all 122 Plan Z subcontracts,
but gave Wight authority over every aspect of the subcontract
process, from developing bid packages to authorizing payments.
 |
|
|
FARKAS
|
"Let me tell you, initially Wight
did not appreciate this organizational set-up, but they listened
well and made it happen," Strauss says. "We were
bringing in a fairly large architectural/construction services
firm from outside the South Bend area to get involved with
a highly visible, demanding and extremely time constrained
project." Convinced that the local expertise did not
exist to satisfactorily meet all of the projects demands,
Strauss says he still believed "we had to do something
to keep the local companies that pay local taxes and have
tremendous community involvement connected with this effort."
Wight, too, recognized the challenge.
"We fought the stigma of being the big-time Chicago CM
firm coming to Indiana to run over the local contractor base,"
Osmun says. He credits Raymond and Strauss with making certain
the Wight/DLZ relationship would work. "The superintendent
established our authority as team leader early by empowering
Wight to negotiate DLZs fees. Other consultant contracts
were modified to include a hierarchy of authority, with Wight
prominent. Wight held and managed the budget and therefore
had input across all lines into design and construction problems
and solutions," says Osmun.
 |
|
|
ROTH
|
While DLZs contract was with SBCSC,
Farkas says Raymond set the tone for the relationship from
the start. "We were all in a meeting and she gave us
the word that DLZ would work out and if there was a problem,
to bring it directly to her." To ensure continuity and
consistency, Strauss assigned Jerry Freeman, director of capital
projects, to a full-time role in the project. "For my
staff, and for one years worth of time, there were no
vacations," Strauss says. "This project became a
mission." Strauss handled administrative issues and SBCSCs
changing requirements and relied on Freeman in the field.
He "had an outstanding feel for construction issues,
could get to the root causes of problems most expeditiously
and had unparalleled stature within the local construction
community," says Strauss.
While Strauss acknowledges that "the
multiple contracting method we used added more administrative
cost to the effort and required extra oversight from my staff,"
he says the resulting control was worth the investment. "The
school board wanted that control, they knew how their monies
were being spent and they had excellent accountability,"
he adds. For the Wight/DLZ team, SBCSCs hands-on approach
to design-build proved critical to keeping the job proceeding
on-schedule. "The school corporation rolled up their
sleeves and worked," says Farkas. "They had it all
on the line and they had to get it done."
 |
 |
| The design-build team was tasked
with quickly turning the $50.8-million expectations of
South Bend into reality. |
Tackling the work required a complex
design and construction game plan. Sharing responsibility
with Osmun and Farkas, Wights lead architect for the
project, Tom Roth, had to do more than just design spaces
and structures. He shouldered the burden of interpreting Plan
Zs curricular and social objectives through his designs.
and meeting the individual expectations of the school administrators
responsible for each facility. Tasked with the final responsibility
of implementing the redistricting effort, the school principals
had their own opinions and considerable input into Roths
work. "It was a real juggling act at times," Roth
says. "We were just one little cog in a big wheel,"
says Osmun. "Id realize that in some of our project
meetings [that] Tom had to consider everything else like textbooks,
furniture, curriculum, when kids would start, where the buses
would go, in addition to our construction questions."
Working at breakneck speed, Farkas was
coordinating construction almost as fast as Roth and DLZ could
draw the plansand occasionally faster. When school doors
opened in August 2003, Phase One was done. "We finished
about two seconds before school started," Farkas jokes.
Phase Two of the plan, covering the larger
additions to several of the six key buildings, continued throughout
the school year. Careful coordination was required to ensure
minimal inconvenience to teachers and students. Wight brought
the second phase in well ahead of the December 2004 deadline,
achieving substantial completion in August.
With the project complete, the team members
clearly are pleased with the results. "This team came
together so well because everyone realized that the only way
to move down the path to success was to be on the same bus,"
Osmun says. "The challenge united us."
DLZs first experience with design-build
taught the firm a lesson. An owner that has good participation,
quick response and a good wish list with which to start is
a very good way to accelerate the design process, the engineers
say. Strauss adds, "We did everything we could do to
expedite the decision-making....The owner has to get involved
and there has to be honest, frank conversation."
Public response to the work has been
overwhelmingly positive, but the real proof of Plan Zs
success will take time. Strauss says hes waiting for
the final report card: "Now we need to see those test
scores go up."
By Victoria L. Tanner
The author has provided communications services to the industry
for
more than 20 years, working with general contractors, subcontractors
and trade groups.
All photos by BKR Studios
Inc., Courtesy of Wight + Co.
Click
here for features archives >>
|