|
Phoenix Could Soar With Biotech Project
By Tony Illia

A sleek modern looking building just completed in downtown
Phoenix could transform the city into a biotechnology powerhouse.
The six-story, 173,000-sq-ft structure will lodge the Translational
Genomics Research Institute (TGen) and International Genomics
Consortium (IGC), two high-profile groups seeking to revolutionize
cancer treatment and other complex diseases through post-genome
science.
The $46-million building, which opened Dec. 15, is the first
structure completed in Phoenixs planned 15.8-acre biotechnology
campus on city-owned land that once housed municipal courts
and a historic high school. It had become a vacant eyesore
in the otherwise robust downtown Copper Square area, a 90-sq-block
mixed-use entertainment district. But following a land-use
study conducted three years ago, city officials decided a
bioscience center was the best use for the property. To make
it work, the owner gave the design-build team a wide birth
to meet tenant needs.
The new TGen/IGC headquarters is expected to create 450 high-paying
jobs, totaling $31.5-million annually in salaries, says Christopher
F. Andres, Phoenixs development manager. It is a long-term
urban redevelopment project intended to diversify the citys
economic base by attracting manufacturing and pharmaceutical-related
businesses to the region. TGen and IGC both signed 30-year
lease agreements with some tax and deferred rent incentives,
says Andres. Campus plans also call for another 10 buildings
totaling 1-million sq ft to be constructed over a 10-year
span, eventually employing up to 3,500 people.
But the crown jewel clearly is the trailblazing build-to-suit,
design-build TGen/IGC project, which now serves as the gateway
to Copper Square. "This excellent facility will enable
TGen to further its goal of delivering improved diagnostics
and therapeutics," says Dr. Jeffrey M. Trent, TGens
president and scientific director. "We have the privilege
of fostering efforts that can better the lives of people around
the world through breakthroughs in medical science."
Getting there was not easy. The city of Phoenix competed
against Atlanta and Baltimore to land the new headquarters
and sweetened their chances by promising a new state-of-the-art
spec building within two years. In 2002, it issued request-for-qualifications
to design-build teams who were judged on experience, team
members and project history, among other criteria. Three finalists
then were interviewed by a 10-person panel about programming,
schedule and concepts. Project costs were only outlined after
a design-build contractor had been selected and the contract
was signed. The undertaking was schedule driven, saving at
least one-year over a traditional design-bid-build procurement
method.
DPR Construction Inc., Redwood, Calif., and design sub SmithGroup
Inc., Phoenix, was awarded the $39.8-million guaranteed maximum
price contract in Nov. 2002. DPR/SmithGroup previously had
teamed on other projects and had developed a comfortable working
relationship. Their familiarity with one another and the project
type helped fast-track design and construction. Architectural
services were provided under a flat-fee contract. The 438-day
project, which carried $10,000-a-day late penalties, opened
one-month later than anticipated due to $3.5-million worth
of scope changes, mostly tenant improvements. As such, DPR
received 27 additional days from the city that eliminated
all liquidated damages. The project finished 2% under budget
with the cost savings reverting to the city.
Making Miracles
To speed the project to market, the TGen/IGC buildings
programming and design came together within 12 weeks, a blistering
pace that is about 75% faster than a design-bid-build approach,
says G. Craig Randock, SmithGroups senior vice president
and design principal. The companys offices serendipitously
are located across from the site, so SmithGroup temporarily
transformed a portion of neighboring office space into project
headquarters, allowing around-the-clock interface with the
contractor, tenant and city officials. The firm also received
a separate $59,000 city contract to develop the sites
master plan, which helped both the building and site layout
come together in a quick and cohesive way. Click
here to view campus plan>>
Although many of the buildings scientists were still
being hired, SmithGroup/DPR drew upon their biotech experience
and teaming relationship to create a flexible floor plan that
anticipated many needs. Walls and floors were stiffened to
meet the structures vibration threshold of 2,000-micro-in.
per second for a rattle-free laboratory environment. And redundant
fiber optic and telephone lines were installed, ensuring constant
service even if one system goes down. The team also added
a 1,000-kW back-up diesel generator so critical work would
not be disrupted by power outages.
 |
 |
| A flexible floor plan anticipates
needs of scientists but also limits vibration. |
"The design-build process enabled us to prioritize our
needs by function and cost during the programming phase in
order to meet the citys budget," says Richard L.
Love, TGens chief operating officer. "Once the
building details emerged, SmithGroup/DPR value engineered
the project to return the items we had identified."
The buildings HVAC demands are tremendous due to the
sensitivity of the electronic research equipment. Through
a novel agreement with Northwind Phoenix LLC, a subsidiary
of APS Energy Services, Phoenix, the TGen/IGC building uses
the nearby Bank One Ballparks central plant, which saved
about $700,000 in equipment costs.
Instead of chillers, three 500-ton plate-frame heat exchangers
were installed in a 10,000-sq-ft partial basement. They interface
with the Bank One central plant, which has 20,000 tons of
peak cooling capacity with centrifugal and rotary screw chillers
and a 36,000-ton-an-hour ice storage tank. The system manufactures
ice each night when utility loads and rates are lowest. During
peak daytime hours, the ice is melted and the water distributed
through an underground network for air-conditioning use in
the TGen/IGC building five blocks south of the plant. The
water then is returned to the icemaker.
The 75-ft-tall cast-in-place structure falls just under the
citys high-rise limit, which made permitting significantly
easier. One major design/construction challenge was housing
the buildings extensive cabling and ductwork as well
as meeting its vibration tolerances while still creating flexibility
for future technology. SmithGroup/DPR used a highly efficient
cost-effective solution provided by Paul Kohler Engineers.
The Scottsdale-based structural engineer devised a scheme
for a high-strength concrete exoskeleton that minimized the
number of interior columns, which are set on a 31-ft-sq grid.
The building also uses high-strength concrete of up to 7,000
lb per sq in. in order to meet the vibration standard. That
is nearly double the strength needed to support a similar
load.
The structure rests atop a foundation of spread footings
and 48 drilled piles, averaging 3 ft dia and 28 ft deep. The
buildings geometry consists of two offset intersecting
rectangles with 10 shear walls for the stairwells and elevator
corridors. The 14-in.-thick mildly reinforced concrete floors,
average 22,500-sq-ft and use a double rebar mat that ties
into shear walls. With no supporting beams or post-tensioning,
there is access through the floor slab, if needed. Using structural
steel would have meant 30-in.-deep beams in order to achieve
the same feat, with no room left for mechanical ductwork,
says Bart A. Rogers, DPRs design-build manager.
Early Payoff
One of the primary tenant mandates was extensive use of glazing
for natural daylight inside all of the laboratory areas. But
Phoenixs cruel desert temperature routinely climbs past
100° F, creating an expensive cooling dilemma. The design-build
solution was a roof-mounted energy recovery system that works
like an engine radiator by using exhaust air to pre-heat or
pre-cool fresh air entering the building. This approach saves
roughly 200 tons worth of peak cooling capacity. Other energy
saving design measures include electronic sensors that shut-off
lights when rooms are not in use and floor slabs that extend
24-in. past the buildings exterior to create shade overhangs.
 |
 |
| Heavy duty mechanical systems
help support project. |
The city is giddy about the outcome. It already has hired
DPR/SmithGroup to do the design and construction for the campus
next $27-million, 60,000-sq-ft phase, which entails renovating
three Phoenix Union High School buildings constructed when
Arizona was still a U.S. territory. The three-story buildings,
listed on the National Register of Historic Places, currently
are undergoing physical inspection. The brick and stucco exteriors
will be refurbished and the interiors modernized for use as
classrooms and lecture areas for the biotechnology park. DPR
is working as an at-risk construction manager and SmithGroup
has a separate at-fee city contract. The contract costs and
specifics have yet to be defined. The project is scheduled
to break ground in the third quarter of 2005.
 |
 |
Signature tower entrance divides
the buildings.
(Renderings courtesy of Smithgroup)
|
 |
| Lobby emphasizes the
clean, crisp and cooling lines of the building. |
Meanwhile, the TGen/IGC building has since sparked additional
plans for the transformation of Copper Square into a medical
sciences corridor. A for-profit venture between TGen and Arizona
State University called Nanobiomics has been set up to specialize
in diagnostic tests and ASU plans to relocate its nursing
and health programs to its downtown campus across from the
TGen/IGC building. The Arizona Biomedical Collaborative, a
coalition of state universities, also plans to locate its
own clinical campus on the TGen/IGC site. And in the TGen/IGC
building, negotiations are under way for the National Institute
of Diabetes and Digestive and Kidney Diseases to occupy the
remaining space.
"Bioscience is the fastest growing segment of the national
economy. Were confident that IGC/TGen and their unique
strategic partnership with the states three universities
and partnering with research organizations across the country
will enhance Arizona's economy by bringing new industries
and new jobs to the state," says Richard M. Mallery,
IGC chairman. "We will keep our best and brightest young
people right here in Arizona."
By Tony Illia
The author is a Las Vegas-based correspondent for The McGraw-Hill
Cos. He regularly reports on design and construction industry
issues.
Click
here for features archives >>
|