|
North Carolina Creating New Culture For
Road Projects
By Mary Buckner Powers
 |
 |
|
(Photo courtesy
of NCDOT)
|
North Carolina Dept.
of Transportation officials are working to revolutionize their
design-bid-build process. They are making major changes to
their bread-and-butter delivery system by incorporating lessons
learned from design-build to construct projects more quickly
and more efficiently.
Department officials stress that
most state transportation projects, which are relatively small,
will continue to be procured through traditional methods but
that they are working to capitalize on the innovations and
positive elements of design-build by incorporating them into
traditional contracts. "With the right emphasis, the
state can develop a process for design-bid-build projects
that will result in more assured costs and schedule,"
says Steven DeWitt, NCDOTs director of construction.
"We know there is a better way out there."
NCDOT has plenty of experience
with both delivery systems. It has awarded $1.2 billion in
contracts per year for the last few years. Most have gone
design-bid-build. But it also has awarded 16 design-build
contracts worth $663 million since 1998, when the state legislature
first approved use of the integrated delivery method. And
it plans to award another $193 million in the second half
of 2005, followed by another $136 million in 2006.
To improve its contracting process,
NCDOT has established an Alternative Delivery Systems Section.
New contracting methods now are in the conceptual stage but
they will mirror the design-build process in certain ways,
says DeWitt. Shortlisting, constructibility, innovation, quality
assurance and better environmental management are high on
the list.
 |
 |
| NCDOT
contract delivery is being speeded. (Photo © 2004
Brian Dressler Photography) |
The new ADS section includes groups
for design-build, value management and alternative contracts,
which is a breeding ground for new types of contract delivery
systems, says Rodger Rochelle, who manages the section as
its chief engineer. "We need people dedicated to the
program to find the lessons learned from design-build and
to keep track of whats good, whats bad and what
can be transferred to conventional projects," he says.
Rochelle is putting together a
group of nine engineers to mirror a private design-build team.
It includes experts in hydraulics, bridges, roadways and traffic
control. They are becoming a self sufficient group that can
handle scoping, establish contracts and deal with submittal
and constructibility problems, just like a private design-build
team, Rochelle says.
Opportunity Knocks
Shortlisting is one of the strongest
design-build elements that can be incorporated into traditional
contracting. "Stronger prequalification programs may
be the most critical of all of the lessons that have been
reinforced through the success of design-build," says
DeWitt. And contractors agree. "It allows us to use innovation
to make a project more constructible and speed them up,"
says Drew Johnson, vice president of the heavy highway division
at Barnhill Contracting, Tarboro, N.C.
But the changes dont stop
there. The state has a list of changes it wants to make in
the design-bid-build process but incorporating them remains
a problem because not all alternatives are applicable to all
projects. The departments challenge is to establish
criteria for deciding which things work best for which projects
and then develop menu models that can be used by the agency
and the contractors. "The challenge is trying to get
people to understand the benefits of these changes and to
get them to try new things," DeWitt says.
One of the first chances NCDOT
had to incorporate design-build principles on a traditional
job was an emergency repair, still under way, of Interstate
40 near Asheville where a rockslide caused a portion of the
highway to slide down a hill. "We wanted to use local
contractors but we wanted to use a prequalified geotechnical
specialist," says Rochelle.
NCDOT put together a design-build
geotechnical package and selected a best- value proposal.
"We told the local contractors that we would make a low-bid
selection but they would have to incorporate the geotechnical
contractor we selected and its plans into the bid," Rochelle
says. NCDOT calls the method a design-build contract "nested"
in a low-bid contract.
One of the benefits is that NCDOT
was able to use local contractors and a specialty design within
existing procedures. The contracting process worked well but
still needs refining Rochelle says. The main weakness is the
risk of selecting a specialty contractor that does not finish
its work on time. "We are working through some of those
issues," he says.
 |
 |
|
Design-build procedures were used
to prequalify geotechnical specialist on I-40 rockslide.
|
NCDOT also inserted design-build
practices into a design-bid-build project that involved very
complex traffic issues. "We gave the contractors a full
set of plans, signed and sealed, but we left traffic control
and phasing up to them," say Rochelle. It was very similar
to a bid-plus-technical proposal type contract. Rochelle says
the department had a concept of how to deal with the traffic,
but the contractors method of dealing with it was very
different. "The department was taking a guess. But why
should we do that when the contractor can tell us whats
best for him," Rochelle says. LPA Group, Columbia, S.C.,
ended up saving NCDOT 16 months on the job because it designed
the traffic flow rather than state designers says Elam Frazam,
vice president of LPAs design-build and construction
services.
On another project with a traffic
control issue, NCDOT traffic control designers said that there
was no way that the job could be done without closing a ramp,
says Rochelle. His group told the design-build contractor
that they were not permitted to close the ramp. "They
found a solution," he says. Rochelles group now
will take the design-builders plan back to department
traffic officials so that they can see how the design-builder
solved the problem. "We have to be diplomatic, but most
people are happy to learn new ways," he says.
Another innovation on Rochelles
list came on a design-build project where the north and southbound
lanes of an Interstate needed to be expanded over a roadway.
Rather than widen the dual Interstate bridges, the design-builder
lowered the grade of the Interstate and built a flyover for
the secondary road. Building the roadway over the Interstate
was quicker, safer and required fewer bridges, says Rochelle.
Design-builders generally build bridges a little differently,
he says. They reduce the number of spans and add retaining
walls at the ends of the bridge to make them shorter. "It
makes for more rapidly constructible bridges," he says.
Some lessons are paying off. Officials
from Blyth Construction, Charlotte, which is part of the Hubbard
Group, Orlando, say that NCDOT was open to its plan to divide
one of its projects into more manageable segments, which allowed
the company to work at its own pace. "NCDOT has given
us the opportunity to bring innovation and ideas to the table,"
says Brian Webb, Blyths construction manager.
While integrating their new procedures,
Rochelle and his group learned that NCDOT designers are not
as current as others on technological developments. In the
past, NCDOT has been very prescriptive about its intelligent
transportation system requirements he says. Once his group
realized that design-builders are more up to date on cutting-edge
technology, it began to rely on the private sector to find
the best technology.
Another important lesson that Rochelles
group learned is that design-builders find problems and ambiguities
in the states design manuals and standard drawings much
faster than designers hired by NCDOT. "They are much
more vocal about the problems," says Rochelle. His group
now tracks the ambiguities that design-builders find. "Its
important to us that we make the changes in the manuals and
the drawings so the problems wont come up again,"
he says.
 |
 |
|
Environmental
permitting procedures are streamlined using design-build
lessons learned.
|
Utility relocation is a good example
and another big hurdle for DOTs because a large percentage
of projects are delayed because of it, says Rochelle. But
after watching design-builders smoothly handle utilities,
NCDOT is taking the same approach. "We offer utilities
incentives to do what they promise, when they promise it,"
he says.
The ADS team also has learned to
think beyond its traditional methods by working with design-builders
on their approach to an environmental permitting problem.
NCDOT learned late that it would need an environmental permit
on an I-77 project. "Normally, we would delay the bid
until we got the permits. Instead, we told the design-build
teams to design [the project] as normal and to prepare the
necessary documents for a permit or to design it to negate
the need for a permit. We let the economics dictate,"
says Rochelle.
All of the teams designed the project
to eliminate the need for a permit. "We saved 15% on
the cost and avoided a full construction season just by avoiding
the permit," says Rochelle. Ordinarily, NCDOT would have
thought it was necessary to go through the normal permitting
procedures, says Rochelle. "The permit alone would have
taken a year and a half to acquire."
NCDOT also has learned to handle
interaction with environmental agencies in a less formal manner
by watching design-builders at work. Rather than seeking environmental
concurrence through large formal gatherings of 20 people,
Rochelles group holds informal three-person meetings
to iron out problems. These are the types of techniques that
are being tracked in the hope of applying them to design-bid-build.
"We are taking out bureaucratic steps here and there,"
he says.
Working Together
In the NCDOT world, each design unit does their piece of
the puzzle but it is not until the contractor gets the job
that anyone looks at the big picture, says Rochelle. "Maybe
our design is less expensive, but as part of the bigger picture
it might make the project more expensive or take longer,"
he says.
As an example, Rochelle says NCDOT
may design a narrow bridge but a design-builder might make
it wider, which may increase upfront costs but expedite the
project and save money in the long run. NCDOT now has upfront
external reviews by contractors of its designs so they can
advise the design team on potential time and cost saving measures.
"We see that a lot of what weve done in our design-build
jobs for NCDOT has been incorporated into their own methods,"
says Wayne Moody, HDRs transportation section manager
for the Carolinas. "The department has shown a willingness
to take the lessons learned from one job and carry them forward
to the next one."
One thing they all learned is that
design-build teams move quickly so the NCDOT design-build
team also is training to act with equal speed. "We dont
wait two weeks for a response any more. We pick up the phone
and say can we meet tomorrow," Rochelle says.
That approach has raised the bar for other groups within NCDOT,
creating a culture of efficiency.
To save time, Rochelles group
has learned to review contracts only to meet state requirements
and safety standards. "Were not checking the exact
numbers anymore. If a contractor made a calculation error
on the amount of concrete needed for the project, its
not our problem," he says. Reducing analysis allows NCDOT
to return documents to contractors within 10 business days.
"Outside of the design-build group, it can take 30 to
40 days," Rochelle says. Now, the traditional department
group is beginning to move more quickly as well, he says.
Rochelle says he also has had to
learn to let go of his control over the details of the projects.
"The design is sealed by a P.E., I have to realize that
hes as good as I am. Ill check what I have to
check, but I wont check the details," he says.
 |
 |
| NCDOT
learned that teamwork produces quick, cost effective and
quality projects. (Photo courtesy of NCDOT) |
The department even learns from
design-build proposals that it does not use. It pays a stipend
for proposals from short-listed teams that are not selected
and studies them to look for ideas. "It may not have
been viable for that project but it may be for one down the
road. So we save it and implement it later," Rochelle
says.
"NCDOT is trying to think
outside the box and is open to changes that reduce costs.
It has made officials and contractors feel more comfortable
about changes and alternative designs," says Barnhills
Johnson.
Word of the efficiency of the new
methods now is circulating throughout the agency. "Folks
are starting to come to us and are asking about our successes,"
says Rochelle. The group plans to publish a newsletter and
develop a Website with periodic reports on lessons learned.
A critical reason for the success
is that the NCDOT support runs all the way up to Secretary
of Transportation Lyndo Tippett, says Rochelle. Ultimately
the most important change within the department is in the
people. Rochelle no longer will tolerate an attitude of "its
not my job." He expects his people to understand that
they are all working toward a common public goal and that
joint efforts promote efficiency and higher quality work.
"We are all working together to get the quality we expect,"
he says.
Click
here for features archives >>
|