|
Coastal Communities Turning To Vacuum
Sewers
By Tom Nicholson
Teaming designers
and builders in integrated project delivery has streamlined
work on numerous building and road construction projects,
saving time and money and freeing owners from change orders
and multiple contracts. Now, design-build project delivery
also is showing up on underground pipe-laying projects where
contractors work side-by-side with designers in developing
optimal plans before digging in.
Thats how things worked out
over the past two years on a sewer project in Ponte Vedra,
Fla., where Jacksonville-based Callaway Contracting Inc. teamed
up with Coral Springs-based Eckler Engineering Inc. for a
$10-million design-build job commissioned by the Jacksonville
Electric Authority. The project involved construction of an
innovative Airvac vacuum sewer system in the 672-home Ponte
Vedra Beach subdivision, which previously had individual septic
tanks for each home. The work included burying 45,000 ft of
6 in., 8 in. and 10 in. PVC pipe, installing one valve pit
for every two homes and constructing a pump station with three
25-hp vacuum pumps capable of moving 450 cfm of wastewater.
JEA merged with the Jacksonville
Public Works Dept. in 1997 and now operates JEA Sewer System,
which includes six regional wastewater treatment plants and
2,500 miles of collection lines. The state ordered JEA and
St. Johns County to install a sewer system at Ponte Vedra
after the state Dept. of Environmental Protection conducted
tests in nearby lagoons and found contamination from the subdivisions
hundreds of septic tanks.
The high water table in the ocean-side
community compounded the pollution and also would have complicated
construction of a gravity sewer system, which would have required
deep trenches. "JEAs typical method of sewer collection
has been traditional gravity," says JEA spokesman Greg
Corcoran. "After quite a bit of research, JEA became
convinced that vacuum sewer collection could provide an acceptable
alternative and, given the right conditions within a project
area, the use of vacuum could potentially be installed at
a cost savings over traditional gravity. Ponte Vedra provided
these favorable conditions so vacuum sewer became the system
of choice."
Click here to view rendering
With cost savings in mind, JEA
and county officials opted to do the project under a design-build
contract. "JEA felt the design-build method of delivery
was best suited for this particular project [because] the
vacuum sewer technology was a new system for JEA and we felt
the use of a design-build firm would provide the expertise
needed to design and build [it]," Corcoran says. "The
goal was to create a concept of total responsibility
for the design-build team." JEA is a knowledgeable owner,
having previously used design-build on upgrades to wastewater
treatment plants and new chilled water plants and felt comfortable
applying it to a sewer grid.
Leading Edge
 |
 |
|
Vacuum system uses smaller diameter,
lightweight pipes and shallow trenches. (Photo by Ed
Stephenson)
|
JEA published a request for qualifications
for the job in mid-2003, and after reviewing a pool of eight
respondents, short-listed three firms. Calloway got the nod,
despite its lack of experience with design-build or vacuum
sewer projects. It was a selection based largely on their
past working relationship with JEA. "We had done about
$50 million of work with JEA before, doing water lines and
pipe laying projects," says Callaways project manager
Stan Bates. "We had never done design-build before and
it was also the first time for JEA on a sewer project, so
this was a learning process for both of us."
Corcoran says respondents were
evaluated for qualifications in safety, project-related knowledge,
record of past performance, resources and financial responsibility.
"Although many exceptional teams responded to the RFQ,
JEAs evaluation team felt Callaway Contractings
abilities gave them the edge over their competitors,"
he says.
With Callaway in the drivers
seat, the next step was for it to choose a design firm as
well as determine which vacuum system would be best suited
for the job. "We talked to two vacuum sewer companies
about their product and also asked if they could recommend
an engineer for the job," says Bates. "In the end
we felt Airvac was the superior product."
Rochester, Ind.-based Airvacs
prominence in the vacuum sewer field, and its comprehensive
support plan were big factors in the companys favor.
Airvac provides clients with an onsite field representative
during construction who stays on location for the jobs
duration to assist contractors with the installation. The
company also offers a week-long training program as part of
its contract in which owners can send two representatives
to the companys Rochester training facility. When possible,
Airvac also will arrange long-term operational support from
a qualified technician if one is located nearby.
 |
 |
| Premanufactured
collection tank module is dropped into concrete block
vacuum station. (Photo by Ed Stephenson) |
For the design duties, Airvac representatives
recommended Eckler, which had done several other Airvac jobs
in Florida, including a project in Palm Springs in 2001 involving
15,000 ft of pipe. Ecklers experience with vacuum system
technology was highlighted by its work with the U.S. Environmental
Protection Agency, which has asked the firm to assist in writing
federal standards for the burgeoning technology.
"When we talked with Eckler
it felt right, it felt like it would be a good team,"
Bates says. Eckler was onboard not only to draw up design
plans, but to lend Calloway its vacuum sewer experience and
guide the team through the installation process.
The team broke ground in December
2003 and finished by May 2005. The time frame of just under
two years is much faster than a comparable gravity sewer system.
Time was saved by using integrated project delivery and the
much shallower pipe depths made possible with the vacuum sewer
system. "The deepest lines were about 8 ft and the average
depth was between 4 ft and 6 ft," says Bates. "With
gravity systems, you are at depths of 20 ft to 21 ft, which
is very disruptive and time consuming. That made this job
very easy, relatively speaking."
Design-build delivery helped the
team trim time by tapping the contractors opinion during
the design phase, enabling Eckler to establish the best, most
efficient, design plan. What resulted was a design that called
for the pipe to be buried beneath the roadway, as opposed
to alongside of it, which at first seemed the likely place
to lay the pipe, says Eckler President Don Eckler. Before
drawing up a design, "we asked, Whats best
for the contractor in this?" says Eckler. In response,
Callaway pointed out that the swale was so full of utilities,
including all the subdivisions electric and gas lines,
that "it would have made it extremely difficult to dig
and lay the pipe there," Eckler says.
The plan to lay pipe under the
roadway was was made even easier by the fact that St. Johns
County already had removed much of the road surface in the
subdivision in preparation for a resurfacing project. "We
saved a tremendous amount of time doing it that way,"
Eckler says. "We were able to see the design from the
contractors standpoint and we came up with the best
design because of that. That was a result of working in a
design-build environment."
Although it was a design-build
job, the contract required Eckler to submit completed designs
before construction began. "It wasnt a typical
design-build job in that aspect," says Eckler. "But
since we were teamed with the contractor we were able to work
with them throughout the design process." That provides
"a whole different mentality" than traditional project
delivery, says Bates. "Its worked out well with
Eckler. They would advise us on the way things should be done
and then we would apply it in the field," he says.
 |
 |
|
Airvac field services technician (in
red hardhat) helps supervise valve pit installation.
(Photo by Ed Stephenson)
|
Ecklers vacuum system experience
came into play when the engineer suggested that the vacuum
be tested on a daily basis at the end of the workday, a frequency
that is above and beyond whats required. "That
was not part of the contract but they asked us to do that
and that was based on their experience," says Bates.
He explains that as pipe is laid, the vacuum pressure must
periodically be tested to determine how much energy is lost
due to distance from the pump, or from diverting up and around
other utility lines. "We followed their advice and tested
daily," Bates says. "It was a good idea that helped
us foresee any conflicts down the road. If there was loss
of vacuum we would know where it was before we got too far
along."
Sweet Success
Vacuum sewer technology emerged
about 30 years ago as an alternative to gravity systems where
geography or limited work zone space made deep digging impossible.
With technology advances, vacuum sewer systems are gaining
viability among designers and contractors, not only as a last
resort in special circumstances, but as an option based on
its own merit and strengths.
The typical system works like this:
A pump station containing three 25-hp pumps is installed centrally
to the scope of the system. From each home, a gravity service
line of small-diameter PVC pipe connects to a sump valve in
a fiberglass valve pit, typically buried just outside the
homeowners property line. The Ponte Vedra job used 359
such valves.
The pneumatically operated valve
opens when 10 gallons of wastewater accumulates in the sump.
Air from an intake pipe that emerges above ground at each
home then breaks the seal in the pit and allows the water
to be pulled by the vacuum through the sewer lines toward
the pump station.
The sewer lines are installed with
a slight slope toward the vacuum station. The lines are placed
in vertically zigzagging "saw tooth" patterns that
take advantage of gravity flow and vacuum assist. Lines use
45° elbows to go around obstacles such as utility lines.
Sewage is sucked through the mains at a rate of 15 to 18 fps
to the pump station and is collected in a tank until it is
forced out into a gravity main that carries it on its way
to a treatment plant.
On level terrain, a vacuum station
can serve up to 1,200 homes through mains up to 10,000-ft
long. There typically are three pumps housed within the station,
but the operation relies mainly on two, with the third serving
as a backup that kicks on during peak hours. The pumps run
on electric power.
Airvac has installed a total of
250 vacuum sewer systems in 27 states. Company spokesman Rich
Naret says its use is contingent on geography, noting that
the system needs level ground for operation and is not viable
for hilly terrain. "Its being used mostly in coastal
areas," says Naret. "It works well in a place like
Ponte Vedra where it is flat. It is good for jobs where there
is a high water table like along the coast in Florida or other
coastal states. One of the hottest places right now for us
is North Carolina."
Vacuum sewers are attractive to
owners because "there are no manholes and no odors,"
says Naret. "And since excavation is not as wide or deep
as on a traditional system there are no trench walls, which
is a safety issue. Trench cave-ins are never a good thing.
Installation is generally less intrusive than with a gravity
system."
Time saved through shallower excavation
cuts construction costs, but Naret says that owners considering
vacuum sewers must weigh reduced installation costs against
the costs of installing necessary components, such as the
vacuum valve pits and a pump station. "Theres really
a trade off," Naret says. "Its less expensive
but there is also a big pump station that has to be built."
Naret says vacuum sewer projects
are beginning to be performed more frequently as design-build
jobs after a slow start in general for sewer work. "Utility
sewer work has mostly gone the traditional route," Naret
says. "Design-build is popular for things where you can
see a structure. Its a bit different with underground
work because you cant see it and it has taken a while
for underground work to catch up with design-build."
Other design-build vacuum sewer
projects include a 259-valve Airvac installation that was
completed in 2003 in Provincetown, Mass., by the team of North
Harwich-based contractor Robert B. Our Inc. and Wakefield-based
engineer Metcalf & Eddy Inc. One massive project currently
out to bid is an estimated $180-million job in the Florida
Keys town of Marathon that is scheduled to be completed in
2010. That project will involve 1,600 valves and seven vacuum
pump stations and will service 10,000 homes.
Click
here for features archives >>
|