U.K. Speeds Traffic and Bridge Design
By Peter Reina
 |
 |
|
(Photo courtesy of Carillion)
|
Drivers
to the Isle of Sheppey, located in Southeast England, have
plenty of time to watch a new $145-million viaduct sliding
into place from both shores of the Swale waterway as they
wait for the 45-year-old Kingsferry vertical lift bridge to
let them pass. Because navigation gets preference to traffic
crossing the islands only bridge, the new design-build-finance-operate
viaduct promises long overdue congestion relief by next summer.
Though deck erection is still months
from completion, the 1.25-kilometer-long structures
sleek outline, as defined by government designers, already
is clear. Keeping the profile sympathetic with environmentally
sensitive surroundings was a key constraint in the contractors
efforts to make the bridge economical to erect.
"Our biggest concern with
[the viaducts] low profile and thin structure was how
it would fit in with the landscape," says Kevin Reid,
design manager with the bridges turnkey contractor,
Carillion Construction Ltd., Wolverhampton. Carillion Group
also will finance and maintain the structure.
Next May, the four-lane viaduct
will start carrying traffic over the Swale and adjacent mud
flats on 19 spans, ranging from 44-meters to 93-m long. Eighteen
pairs of concrete piers, five of them in the water, are now
complete with some tapering to 3-m diameter at their tops.
The tallest reaches 29-m above ground. Piers are each supported
by 12 piles up to 1.5-m-dia, cutting through 10 m of surface
alluvium and down a further 30 m.
 |
 |
|
Jacks and strands located on both
sides of the Swale advance steel girder sections in
incremental launches at 10 m per hour. (Photo by Peter
Reina for Design-Build)
|
Spanning between the pier tops
is a deck structure of four longitudinal girders. They range
from 1.8-m to 3.2-m deep and are set on 5.5-m centers. Including
secondary beams, the deck will contain 10,000 tonnes of steel
fabricated 300-km away in South Wales. They will be topped
with a 25-cm-thick reinforced concrete slab cantilevering
2.5-m from either side.
When completed, the viaduct will
handle most road traffic onto the island, leaving the lift
bridge mainly for the railroad. Until then, the two-lane lift
bridge is the sole means of access for rail traffic and 25,000
vehicles a day traveling to the 90-sq-km island. With a population
of some 35,000 people, the island is largely agricultural.
But it also supports some industry and a dock at its main
town, Sheerness, which serves ferries to continental Europe
and handles nearly 1 million tonnes of fresh imported produce
a year.
Speedy Delivery
To ease access to the island, the national
Dept. for Transports English Highways Agency in the
mid-1990s increased from two to four lanes some 8 km of road
linking the M2 motorway to London, 50 km away, and the Swale.
To complete the 17-km upgrade to Sheerness, on the islands
opposite side, the government chose in 1998 design-build-finance
and operate procurement.
"Pretty much, the Highways
Agency has moved away from traditional methods [except] for
smaller schemes," says Graham Link, the agencys
project manager (see box). As well as letting the contractor
raise necessary financing through its own equity and bank
loans, the approach also increases contractor design input,
he adds.
Carillions contract covers
construction of the viaduct plus over 5 km of dual two-lane
island-side highways. After construction ends, the Carillion
Group will maintain the entire 17 km, including new sections
till 2034.
Because the road and bridge will
be toll free, Carillion will earn fees linked to other factors
such as lack of closure. Including maintenance and operations
over the whole 30 years, the contract is valued at around
$180 million at todays prices, according to the Highways
Agency.
To win the contact against three
rival groups, Carillion set up its bid vehicle, now the concessionaire
Sheppey Route Ltd., and spent much of 2002 forming its proposals,
says Mark Robinson. He led Carillions bid team and now
is a director of Sheppey Route.
For the bidding and subsequent
construction, Carillion assembled a team of familiar firms.
Because of its marine engineering skills, Edmund Nuttall Ltd.,
Camberley, was hired on a "near enough lump-sum basis"
to do the substructure, says Robin Daniels, Carillions
project manager. For the deck, Carillion recruited two small,
specialized firms with shared histories and both based in
the same town of Chepstow, South Wales.
Reporting revenue of about $40
million annually, steelwork subcontractor Fairfield-Mabey
Ltd. traces its history to early 19th century bridges. One
of its former engineers left nearly 25 years ago to set up
Carillions project superstructure designer Cass Hayward
& Partners. With about 30 staff, Cass Hayward specializes
in bridges, mostly in design-build contracts, says partner
Alan Monnickendam. "Weve worked with Carillion
many times before," he adds. Accustomed to more modest
bridges, "this is certainly the biggest project weve
done," he adds.
|
U.K. Looking Beyond Design-Build
Ever
increasing integration of design and construction has
been a hallmark of the U.K.s Highways Agencys
procurement since it began embracing design-build more
than a decade ago. The trend accelerated with the desire
to privatize highway delivery through design, build,
finance and operate contracts that took off in the mid-1990s.
The Sheppey Island bridge project is one of the last
of 11 DBFOs signed in England since 1996, each worth
up to $440 million.
But
not all projects are suitable for private financing.
So the Agency awarded its first contract two years ago
under a new process called Early Contractor Involvement
(ECI). Design-build was fine, but we wanted to
get the contractor in even at an earlier stage,
says an agency official. One of the biggest ECI contracts,
signed earlier this year for $430 million, will add
one lane each way to 17 km of the dual three-lane M1
motorway north of London.
In
the initial 44 weeks of the project, a joint venture
of London-based contractors Balfour Beatty Construction
Ltd., and Skanska Construction U.K. Ltd. will review
existing plans, develop outline designs and agree to
a target cost. In November, the joint venture will start
detailed design and construction, completing work around
May 2008. In this project, statutory procedures had
been completed before the award. In other ECIs,
the contractor helps the agency with those too.
Bidding
for ECI contracts is based on 100% quality adjudication,
says Steve Tarr, managing director of Balfour Beatty
Highways. Until construction starts, the contractor
earns fees. Then payments are based on real costs, including
overhead and agreed profits. For added incentive, the
contractor and agency share savings or overruns in prescribed
proportions.
Both
the agency and contractors agree ECI is beneficial.
Procurement has a fundamental role in delivering
high quality services, says Steve Rowsell, the
agencys procurement director. We will continue
to show leadership as we learn more about the extended
supply chain, ensure integration into the planning and
design processes and make it clear to our suppliers
what is expected of them.
But
there are also risks. After completing planning, a proposed
$360-million,
2.1-km tunnel project in Wiltshire has been dormant
since early this year. The ECI contractor, Balfour Beatty,
had earned its fees developing the scheme and firming
up costs and was anxious to start construction. In late
July, the government ordered other options studied because
forecast costs had risen 65% due to ground conditions.
Certainly its quite frustrating,says
Tarr. We put in three years of effort.
|
Bridging Beginnings
From the start, the subcontractors "were
intimately involved in the design process. [They] attended
numerous meetings, which paid dividends," says Daniels.
Bid designs were taken far enough along "to allow us
to produce a detailed price and establish quantities and construction
methods," he says.
 |
 |
|
The low-profile composite steel plate
girder bridge was approved by a fine arts commission.
(Photo courtesy of Carillion)
|
The Highways Agencys reference
design for the bid was a steel twin box girder, outlined by
Mott MacDonald Group, London. Approved by the government in
the mid-1990s, the project had gone through substantial development.
The agency also had managed environmental studies and taken
the project through a planning inquiry, fixing the bridges
main features, says Link.
However, contractors design
alternatives were welcome. "Very early, we looked at
various options and one of those was to replace the [box]
deck with composite steel," says Robinson. Apart from
any other reason, handling box girders would have been difficult
in the cramped site. Carillion even considered using concrete
but "fairly quickly" settled on steel, he adds.
Approved by the governments
advisory Royal Fine Arts Commission, the Highways Agencys
slender design was intended to minimize the impact on the
flat marshy, estuarial island. It is so rich in birdlife and
other fauna that it officially is listed as an important conservation
area.
The contractors design variant,
"has got exactly the same performance [as the reference
design] and the depth is pretty much the same," says
Reid. To help with the aesthetics, Carillion hired Yee Associates,
London, an architect specializing in international bridge
design.
During bidding, the construction
methods and structural designs were intricately connected,
says design manager Reid. "Only once we understood how
we were going to build it could we design the permanent works,"
he says. "For 18 months, we have been holding, every
other week, design review meetings with [designers and contractors],
ourselves." Designers of the construction systems were
included, he adds.
For example, rather than pre-camber
the girders the contractor made them straight. During launching,
the girders bent under self weight into their final profile.
That meant more steel to take the extra stresses but "the
investment allowed us to have a much simpler form of construction,"
says Reid.
With bids lodged in December 2002,
the Carillion team emerged as preferred bidder the following
February. Carillion and the Highways Agency then knuckled
down to negotiations, ending with contract signing a year
later. "There were various issues that needed to be resolved...in
terms of compulsory purchase and agreement with third parties,"
explains Robinson.
 |
 |
|
Eighteen pairs of concrete piers will
support 19 spans ranging from 44 m to 93 m long.
|
 |
|
Long overdue congestion relief and
speed to market prompted the Sheppey Island project.
(Photos by Peter Reina for Design-Build)
|
Starting main construction in June
last year, Carillion built jetties from both shores to either
side of the navigation span for land access to all areas.
Piling and substructure construction followed with the last
pier being completed this spring. Deck erection is by progressive
launching from both sides, starting this March and due to
end in September.
The decks main framework
is advancing in incremental launches, with temporary nosings
reaching ahead from both sides to awaiting piers. Each of
the longitudinal girders slide over bearings on temporary
frames straddling the column tops. In the end, the deck will
be lowered onto permanent bearings between its cross girders
and the pier tops.
Steel subcontractor Fairfield-Mabey
is trucking 268 pieces of plate girder to the site from Wales
to weld them together and paint them in small tents located
next to the bridge. On the island side, these are craned onto
tall temporary and permanent piers, bolted to the decks
rear and stiffened with bracing. Then, strands attached to
the decks rear are pulled by jacks anchored to the sixth
pair of piers ahead.
On the mainland, the pier tops
are just above ground level. There, the jacks are fixed to
the decks rear with strands anchored to piers further
forward. Jacks advance the sections at about 10-m-per-hour,
says Daniels.
Carillion planned the launching
in three phases, omitting deck sections at three locations.
One missed span is on the mainland shore because of the tight
horizontal curve. Another three missing spans are close to
the island, where they cross the railroad. The last gap is
next to the mainland abutment. To lift deck sections into
these missing spans, "we are bringing in a 1,000-tonne
crawler crane in October," says Daniels.
Concrete decking will be cast on
permanent formwork spanning between secondary steelwork. The
formwork consists of 30-cm wide precast planks, which are
6-cm thick, with looped rebar projecting for their top surfaces.
Carillion will soon take delivery of two different kinds of
travelling gantries that will roll along the deck placing
the formwork and casting the concrete on top.
Carillion has full responsibility
for the viaduct and linking roads till 2034. It then must
pass infrastructure quality tests before handing the route
back to the government. The contractors incentive for
sound construction is, theoretically, set by those long-term
requirements.
|