Team Earns Wings with Flight Training
Facility
By Tom Nicholson
The
Alteon Training Center in College Park, Ga., probably handles
more take-offs and landings than most major airports. Pilots
from around the nation come here to hone their skills at flying
big Boeing jets even though they never leave the ground. The
two fledgling firms who designed and built the facility also
earned their wings by spending plenty of time on the ground
taking care of business.
The design-build team of Southern
Construction Group, Jacksonville, Fla., and Doherty Sommers
Architects Engineers Inc., Jacksonville Beach, Fla. were chosen
for the $5.5-million job in March 2003 by developer Airport
Builders Group, Jacksonville and Alteon, a Boeing subsidiary.
Even though the firms were barely a year old, they completed
the shell in less than 10 months, did some interior build-outs
and scope changes and still came in $1 million under the guaranteed
maximum price. "This was definitely a big project. We
had formed only the year before and we knew this was going
to be an important job for us," says Tony Robison, SCG
president. Caren Doherty, partner at Doherty Sommers, says
she and architect Craig Sommers had formed their architectural
firm little more than a year before landing the Alteon project.
"We saw this job as a way to establish ourselves,"
she says. "Being a new company, we were able to put 90%
of our time into doing the job. It was a big one for us."
It also was a big task for Alteon. The centers five
high-tech flight simulators provide pilot crews with the virtual
experience of flying Boeing 717 and 737 planes, training as
many as 6,200 pilots annually.
 |
 |
|
Pilot crews from Airtran Airways and
Midwest Airlines will be trained at the new facility.
|
The flight training facility involved
construction of a 52,000-sq-ft two-story building to house
the training centers classrooms and administrative offices,
and a 20,000-sq-ft flight simulator hall with an attached
2,000-sq-ft-room for the hydraulic pumps that power the simulators.
An additional $60-million contract covered the interior fit-out,
including installation of information technology systems and
the simulators, which was done by Alteon subcontractors and
overseen by SCG.
Starting in March 2003, the team
had 10 months to complete the job. The rigid deadline was
set by flight training sessions that already were scheduled
for September, when pilots and co-pilots from Airtran Airways
and Midwest Airlines would arrive to begin their first sessions
on the flight simulators.
The design for the classroom portion
of the building utilized tilt-up construction, which was "fairly
typical of what youd see on an office building,"
Doherty says. But design of the simulator hall required some
special details. "In this job, the client had very particular
needs. The design of the simulator hall had to address ventilation
and cooling of the simulators and the foundation needed to
accept hydraulic lines," she says. To ventilate heat
generated by the hydraulically operated simulators, the design
called for heat exchangers to be placed on the buildings
roof. "Our requirements are extremely different from
a commercial building," notes Tim Turner, manager of
center services for Alteon.
The simulators move during operation,
causing vibration, and the hall needed heavy-duty floors to
support them. "The [concrete] floor had to be strong,"
Turner says. "It had to be at least 16 in. thick to hold
up under the simulators movement, and each simulator
has to have its own concrete pad to isolate the harmonics
from the rest of the building." The hall also had to
be at least 42 ft high and be able to accommodate 400-cycle
power, he notes.
The flight simulators are manufactured
by Flight Safety International, Broken Arrow, Okla. and CAE,
Saint-Laurent, Quebec, and are designed to give pilots life-like
experience in operating Boeing 717-200 and 737 models including
the 300, 700 and 800. The simulators mimic the full range
of conditions pilots encounter in the air and provide virtual
replications of airports around the world, showing the actual
runway to give pilots visual familiarity with each airport.
The simulators, which range in cost from $8 million to $16
million each, can be customized for different training needs.
 |
 |
|
Classroom space was not completed
until the simulators were operational and certified.
|
Although the design-build team
came into the job knowing the core requirements for the buildings
design, the full design details had to evolve as the fast-tracked
deadline-driven project progressed. "We had a good idea
of what was needed, but we had to work closely with the architects
throughout the project and as we went along had to make changes
as [Boeings] requirements were identified," Turner
says. The projects quick pace and evolving design schedule
demanded the speed and flexibility of design-build. "There
was no way this job would have been completed by deadline
if design-build wasnt used," says Scott Ronning,
ABG director.
Old Friends
Ronning, who had worked as an owners
representative and developer on other flight training facilities
in Miami and the U.K. for Alteon did not have to look far
when choosing the right team for the job. He already had formed
close relationships with Robison, Doherty and Sommers on previous
jobs. Robison had recently left The Haskell Co., Jacksonville,
and formed his own contracting company.
"Ronning and I go back several
years," Robison says. "We had done flight training
stations for Boeing while I was a project executive at Haskell.
When I found out he was planning flight training projects
for Boeing, I put together an RFP for the [College Park] project."
Doherty and Sommers also had been on staff at Haskell and
had worked with both Robison and Ronning on Alteon jobs before
partnering together and forming their own firm. "The
key players on the project had all worked together before
in one way or another," Sommers says. "Those working
relationships are important because you already have that
communication that you need on a design-build team. Its
like a band that has played together for years, each member
knows when to take the lead or to step back."
While a request for qualifications
was not published, ABG invited another design-build team from
Atlanta to make a presentation. "They set up a horse
race between us," Sommers says. "We had to do quite
a lot of preliminary plans before we made the presentation
to the client. We worked very closely with SCG in generating
a design schedule. We did a 25% drawing for the presentation.
Since we had worked on designs for flight training stations
before, it was a design problem we were familiar with so we
knew we had a good chance at getting the job."
Although confident their experience
gave them the inside track, Doherty says the architectural
firm invested a substantial amount of time and money in the
presentation. "We spent about $15,000 to $17,000 just
to prepare for the bid," Doherty says, noting that no
stipend was being offered if the contract went to the other
team. "It was a risk but we were confident. I dont
think we would have bid if we didnt think we had a very
good chance."
Early in 2003, Alteon and ABG gave
the go-ahead to the team. "[Robison] had significant
design-build experience and knew about flight simulator buildings,"
Ronning says. "Another big factor in selecting SCG to
lead the team was cost. There was a guaranteed maximum price
of $6.5 million. Alteon is a cost-driven company and SCG came
in ready to answer a lot of the pricing questions that needed
to be addressed. Thats what got them the job."
As the project progressed, design
and construction teams worked in tandem. "It was very
fast paced and we had many design meetings with SCG and Alteon
throughout the design process," Sommers says. "This
was truly a design-build job," Ronning says. "Because
we did the design as construction work was going on, we were
literally digging the foundations on a building we had not
yet fully designed. This was design-build at its best."
The rapid pace and simultaneous
multi tasking of designing and building made team communication
vital, Ronning says. "From when we started the job to
finally handing the key over to the owner, the team was in
constant communication," he says. Robison says success
with integrated delivery requires builders and designers to
work shoulder-to-shoulder. "We were the contractor, but
we took a team approach," Robison says. "We had
a very good, open relationship with the team and that gave
us the ability to react quickly to field issues. With the
architects there, we were able to make suggestions about constructability
and materials during the design."
Midway through the design, the
integrated environment helped the team respond quickly when
Boeing announced a change of plans in the type of flight simulators
the facility would use. "We had to make a change to the
hydraulic pump room," Robison says. "It was designed
for 727 simulators, but that was changed and modifications
were made in the design to fit simulators for the 717 and
737 jets. That could have been a major setback if not for
design-build." Robison says that modification alone could
have thrown a wrench in the schedule of a traditionally delivered
job. "We didnt have to wait for change orders,"
he says. "With integrated delivery, the team roster often
expands beyond the core group of designer, builder, owner
and owners representative."
 |
 |
|
Last-minute design changes were fast-tracked
after Boeing announced changes in the type of simulators
to be used at College Park.
|
College Park city officials also
helped the team avert obstacles that could have thwarted their
need for speed. "Rather than wait for a full set of permit
documents, the city allowed us to do multiple submissions
for documents, which was critical to saving time and keeping
the job moving," Ronning says. "We formed a remarkable
relationship with the city officials and they had a strong
enough comfort level with us that they even did some inspections
with pictures."
Sommers points out that "the
quick delivery was challenging unto itself, but when everyone
is focused on the project, even the city, it becomes much
easier. If we could do a job like that every year Id
be happy."
By September, the simulator hall
was completed and subcontractors installed the machines while
construction on the classroom portion of the building continued
until November. "There were actually training sessions
going on in the simulator hall two months before we had finished
construction on the classroom part of the building,"
Robison says. A phased turnover was required because the Federal
Aviation Administration requires simulators to be operational
and certified prior to customer use. This meant that bays
had to be completed before the certification began.
Subcontractors finished the interior
fit-out by December and Alteon installed the final two simulators
in June 2004. The team finished the job well under the guaranteed
maximum price of $6.5 million, which Robison attributes to
the "sheer speed" on the job, cost mitigation in
the design and economies in the plumbing, mechanical and electrical
systems.
Fast Forward
Today the same design-build team is working
on renovating corporate offices at Altell Stadium, home of
the Jacksonville Jaguars, National Football League team. In
between Alteon and Altell, DSAE and SCG completed a number
of other design-build jobs including a restaurant and a nursery.
Separately, DSAE is teamed with
Southeastern Trenching and Technologies, Jacksonville, for
construction of an 18,000 sq ft building for a food store.
While both firms are working on the same job under separate
contracts, Sommers notes, "Were all sitting together
at the same table and identifying what is needed [to complete
a successful project], which is a key lesson learned through
design-build. [It] certainly streamlines things because everyone
comes to the table with the same goal."
(All photos courtesy of
Southern Construction Group, LLC)
|