Boomtown's Growth Requires Rapid
Response
By Tony Illia
Gilbert,
Ariz., is the nations fastest growing municipality,
adding 1,000 new residents monthly. To meet critical infrastructure
needs, the town turned to a variety of alternative project
delivery methods in its five-year, $622-million capital improvement
program. In doing so it has helped pioneer the use of design-build
delivery in the state.
What was once just a rail siding
on William "Bobby" Gilberts property and then
a sleepy farming community located about 22 miles southeast
of downtown Phoenix, has been transformed into a booming exurb
thanks to annexing 53 square miles of surrounding land in
the 1970s. Gilbert has doubled its population every
five years since 1980 yet is still incorporated as a town,
making it the only town in the U.S. with over 100,000 people.
But there are growing pains. Town
officials have turned to alternative project delivery methods
such as design-build in order to fast-track new roads, fire
stations, schools, parks and water reservoirs to meet burgeoning
demand. Gilbert is now more than halfway into a 350-project
capital improvement program. The rolling program is evaluated
annually and renewed every five-years, funded by a combination
of permit fees, water connection charges, general obligation
bonds and private developer contributions.
While anticipating its infrastructure
needs, the town lacked the needed manpower and expertise to
run a large construction program. In January 2003, it issued
a request for proposals for a program manager. Three months
later, the town hired Phoenix-based PinnacleOne under a lump-sum,
annually renewable contract. It is valued at 1.25% of the
programs total cost, based on a formula of personnel
and manhours, or about $1 million annually. It is money well
spent, say officials.
After securing the contract award,
PinnacleOne spent the first 90 days validating projects, costs
and schedules, while re-sequencing the program to prevent
any conflicts and overlaps, says Daniel B. McCausland, PinnacleOnes
regional director. It enabled the firm to identify and prioritize
time-sensitive issues such as utility relocation, right-of-way
and siting that potentially could delay projects. PinnacleOne
next set about standardizing procurement procedures, progress
payments, documents, contracts and management among the towns
nine divisions.
Municipal agencies often have established
processes in place, something they usually are reluctant to
change. Yet PinnacleOne encountered surprisingly little resistance
to implementing uniform measures and methods, due primarily
to the towns rapid growth and shared sense of cooperation.
The firm even standardized public information meetings as
well as advertising and mailing notices. "When all the
information is clarified and people are informed, its
surprising how little resistance you face when a new project
is introduced in a neighborhood," says McCausland.
After three years hard work, Gilbert
has completed roughly $250-million of projects ranging from
streets and municipal buildings to stormwater and recreation
facilities. The program has 80 to 100 projects under way at
any given time, and it currently is running about 2.5% under
budget. To deliver the goods, the town draws upon a plethora
of procurement tools to meet its different needs. It uses
job-order contracting for traffic signals, for instance, and
construction manager at-risk for streets and roads.
 |
 |
|
Reserviors and pumps are a crtical
part of
Gilbert's development.
|
"Design-build has proved one
of the fastest methods, thus far saving 25% to 30% in time
over traditional design-bid-build delivery, while also creating
single source responsibility", says Paul A. Mood, Gilberts
capital projects administrator. Although the town has a small
oversight staff, its manpower can swell and shrink as needed
through PinnacleOne. It currently has six full-time program
positions including onsite project managers, technical support
and scheduling and estimating backup. Town officials also
have recruited PinnacleOne to serve as construction manager
on individual projects under a separate contract.
Design-build so far has been used
to complete $17.5 million of capital improvement projects,
including three, 10,000-sq-ft, four-bay fire stations under
a prototype design and a 4 million gallon in-ground reservoir
with a 6,000-gpm pump station. A two-story, 35,000-sq-ft municipal
office complex building was finished in April 2002 by Johnson
Carlier Inc., Tempe, Ariz., with Dick & Fritsche Design
Group Architecture, Phoenix. It was the towns first
design-build deal and currently houses Gilberts planning,
building, code compliance, public works, engineering and economic
development departments.
 |
 |
|
A two-story, 35,000-sq-ft municipal
office building finished in April 2002 was the town's
first design-build project.
|
The town presently has nine other
design-build jobs totaling $76.9 million under construction,
including three arsenic mitigation wells and a 2-million-gallon
reservoir and a 6,000-gpm pumping station. Another $37 million
of projects is under design.
Click here to view pdf chart
They are needed fast. Between private
and public projects, the town currently is issuing 350 building
permits per month. There is at least $23.2-million worth of
additional design-build work scheduled for fiscal year 2005-06.
Big Squeeze
The projects sometimes overlap and coordination
becomes critical. Sundt Construction Inc., Tempe, is the design-build
contractor for a 21,000-sq-ft, five-bay, brick fire station
and a two-story, 65,000-sq-ft tilt-up concrete police evidence/fire
warehouse facility located on the same site. It has a guaranteed
maximum price contract totaling $20.3 million. Detroit-based
SmithGroup Inc. is the project architect under a fixed-fee
subcontract.
 |
 |
|
Shared fire station headquarters and
police substation project was condensed to 19 months.
|
Shortly after the contract award
in November 2004, Sundt isolated $3.1-million worth of work
consisting of site grading and advance material purchases
on longer lead time items such as masonry block and steel.
The move enabled the contractor to begin work immediately
on the 19-acre site while design still was under way and lock
in materials pricing in an unstable market. The fire facility
will serve as battalion headquarters, using an emergency response
system that interfaces with the neighboring town of Mesa.
"Different users with concurrent
projects on a shared site could spell disaster, but progress
has been smooth thus far," says Brian Kearney, Sundts
project director. "By bringing the stakeholders together
for weekly and monthly meetings, there has been a clear exchange
of information outlining needs and expectations."
The challenges were compounded
in July when the town asked the design-build team to accelerate
its schedule by four months in order to better coincide with
Phoenix-based Pulice Constructions completion of a $54.1-million,
3.5-mile upgrade of the Santan Loop 202 Freeway. The freeway
corridor is the towns main artery and the new police
and fire station will be needed as new major commercial and
medical facilities open along the route. Gilbert officials
are tapping into a 1% contingency fund for overtime hours
to meet the new June 2006 deadline. It will condense the two
projects time to 19 months.
Adding to the difficulties is yet
another concurrent project at the same site. PCL Construction
Enterprises Inc., Denver, with Wilson & Co. Inc., Engineers
& Architects, Albuquerque, N.M, have a $5.9-million design-build
guaranteed maximum price contract for a 2-million-gallon in-ground
reservoir, a 6,000-gpm pump station and a 1,500-gpm well that
runs through the middle of the same 19-acre property.
The overlapping schedules called
for PCL to be onsite before Sundt and finished before the
new police and fire station facilities come online. To head
off conflict, the two teams met ahead of time to map out logistics
for staging and storage, trailer placement and delivery times.
"There has been an accommodating attitude since each
contractor is dependent upon the other to meet its schedule,"
says Brian Taylor, PCLs project manager.
  |
|
The $25 million
South Area Service Center, Public Works Facility &
Police Substation, is one of several design-build projects
now under way.
|
Give-and-take has enabled each
team to work comfortably within a shared space. PCL, for instance,
excavated 16,000 cu. yards of material for its project and
shared half of it with Sundt to use as backfill and foundation
base. Sundt, in return, helped procure some added storage
space for PCL on a neighboring property. "Completing
complex, interlocking projects on tight schedule couldnt
happen without the sense of ownership and involvement that
design-build fosters," Mood says. "It has been invaluable
in helping us meet the demands of rapid growth and speed delivery
time for critical community infrastructure."
(All photos courtesy of
town of Gilbert)
|