Hybrid Design-Build Delivery Breaks
Barriers
By Mary Buckner Powers
Cramming
12 months worth of work into nine is rarely an easy proposition.
Add to that an increased scope and a remote site without water
or power and a contractor can be pushed to its limits. Then
tack on a language barrier and a difficult project becomes
an unrelenting challenge, even for a design-builder.
"A lot gets lost in translation,"
says Mike Waller, project executive for Brice Building Co.,
Birmingham, Ala. Brice and its joint venture partner, Marshall
Construction LLC., Montgomery, Ala., designed and built a
500,000-sq-ft stamping plant in Luverne, Ala., for a South
Korean company called SMART, Stamped Metal American Research
Technologies. SMART Alabama LLC supplies interior door panels
and floor pans to the Hyundai plant in Montgomery that began
producing vehicles in May 2005.
Hyundai announced in 2002 that
it would spend $1 billion to construct its first U.S. manufacturing
plant in Montgomery to build the Sonata sedan and the Santa
Fe, a small SUV. SMART Alabama is the largest of about 35
suppliers that have built plants in Alabama to provide parts
to Hyundai.
The Luverne plant was SMARTs
first manufacturing plant in the U.S. The firm was used to
doing business as it does in Korea, so there were cultural
and linguistic differences that resulted in many meetings
and memos. For instance, it took many back and forths just
to finalize the design of the small, 22,000-sq-ft office space
because American designers are not used to Korean office layouts.
Obtaining design approvals took
time. "Coordinating design is more difficult when dealing
with people with limited English, and we were certainly limited
in our Korean," says John Marshall, president of Marshall
Construction. And language still is a problem.
Marshalls role in the joint
venture was to coordinate the design of the plant, which is
its specialty. Brice coordinated the construction and self-performed
about 20% of the concrete work.
Marshall is a small privately owned
company that does most of its work using design-build delivery.
It generally subcontracts out the architecture and engineering,
but teams with a partner on larger jobs, such as the $25-million
SMART project. The company normally does about $30 million
a year and has 39 employees. "We subcontract everything
out, design and all construction," Marshall says. On
the SMART project, a major challenge was getting good, clear
technical information, he says.
Building Blocks
The SMART plant was modeled largely on a plant in Korea,
and the joint venture was tasked with gathering information
about what the company wanted to build before developing a
proposal. Getting answers was sometimes tedious. It was not
uncommon to ask the same question three or four times in three
or four different ways. "Often we thought they understood
when they didnt. We had to be very patient," says
Brices Waller.
The project used a hybrid version
of design-build, which included construction management. "It
was a blend of CM and design-build," says Marshall. "We
coordinated the design and the construction but we also had
the transparency of a construction manager."
Unlike an agency construction manager,
the joint venture signed the contracts with the subcontractors,
as a true design-builder would do. But the joint venture shared
information with the owner as if it were a construction manager,
Marshall says. The joint venture also agreed on a percentage
of profit at the beginning of the project. "That made
the Koreans feel very comfortable, and made it a lower stress
experience for them," Marshall says. He notes that the
key to the projects success was its openness. "The
Koreans wanted the cheapest price and we offered them transparency,"
he says.
Every bid was shared with the owner.
The Koreans wanted to see the costs, but it was Marshalls
job to help them understand which bids were best. The advantage
of the local builders expertise is critical at that
stage, says Marshall. "We know which subcontractors may
be unable to perform. We know the quality of their work or
whether theyre just too busy," he says. Marshall
sent bid packages to companies it felt were qualified to perform.
The project was so successful that the design-build/CM system
became the delivery method of choice for most of Hyundais
suppliers, say joint-venture officials.
Because of the fast-track nature
of the project, there was no time for value engineering after
the bid packages were issued. Instead, the design-builder
budgeted different options during the design process. The
owner was given options, with the advantages and disadvantages
and costs of each option. The design was completed based on
the SMART officials choices.
 |
 |
|
|
|
Use of a hybrid design-build/CM delivery
increased the Korean owners' confort level.
|
Some parts of the design did not
always have the lowest cost. Several times, when bids came
back, the owner wanted the packages sent out to several more
companies. "It usually wasted more time rather than saving
money. Never did a bid come back low enough to justify the
two-week delay," Marshall says.
The biggest lesson Marshall learned
was the benefit of transparency. "We use it on all plants
now," Marshall says. "With profit margins as low
as they are today, there is no reason not to show the numbers
to the owner," he says. "Usually theyre shocked
at how small the profit margin is and they mostly feel sorry
for us."
The scope of the project included
a 120,000-sq-ft stamping area, a 360,000-sq- ft assembly area
and the 22,000-sq-ft office. The building has a structural
steel frame, with 98-ft long and 67-ft wide long-span bays.
Tons of Fun
 |
 |
|
SMART stamping plant is heavy on robotics
to meet surging demand for
Hyundai vehicles.
|
The stamping area was designed to hold four large presses
capable of stamping metal sheets with a force of 2,300 tons
per sq in. The 20-ft deep foundation for the stamping pits
had walls 4 ft thick and base slabs nearly 6 ft deep. The
press area has a ceiling height of 61 ft and seven overhead
cranes, along with one freestanding crane. A 550-ft long scrap
tunnel runs the length of the building and connects the four
press pits. The 34-ft high assembly area holds hundreds of
robotic welding machines that assemble the stamped parts into
completed components.
The design had to accommodate very
large and complex machines with strict tolerances. It required
detailed coordination with the equipment manufacturers to
ensure that the foundations were built to their specifications.
To add to the complexity, the owner changed equipment manufacturers
and equipment layout after design began. That, in turn, delayed
the electrical design, which had its own set of challenges
because of the international sourcing of the plant equipment
and their varying power requirements.
Despite the fast track, the design
team could not force the owner to make quick decisions. "It
took many phone calls, four- to-six hour design meetings and
many file transfers," Waller said.
The design also needed a fair amount
of flexibility. The design-build team knew the loads and the
machines the building would house, but it did not have the
exact layout. "We designed around the total projected
load, but there were a lot of details we did not know,"
says Waller. "We had a responsive design team, so we
were able to stay ahead of it. They kept an open mind and
didnt panic."
With the delay in the final layout,
it was the design-build process that made it possible to meet
the tight schedule, says project manager William Tynes. "Getting
approval for the various bid packages slowed the project down,
which made the schedule even tighter," says Tynes. "The
owner required multiple approvals and just when the company
thought an issue had been resolved, the owner would come back
with something totally different."
The delay in the steel package
delayed the fabrication and, in turn, delayed the installation
to the point where the subcontractor had just 10 weeks to
complete the job. That required working seven days a week.
The installation started in January and had to be completed
by March 9. "It was a very tight schedule at the worst
time of year," says Tynes. Then the owner added another
stamping pit to the design after the steel erection had begun,
which meant it could not be built until after the steel erection
was completed and required shoring and construction in a tight
area, Tynes said.
All parts of the project were designed
and built in sequence. The delays in obtaining design approvals
tightened the schedule, but never slowed the project. "We
never had to wait. But we got as close to waiting as we could
get," says Tynes. The delay in the steel came when the
design-builder authorized one steel company, but the owner
changed its mind and decided to go with another company. "We
got it straight, but during that time, the steel wasnt
being ordered," Tynes says.
Adding to the fast-track challenge
was the sites remote location, which is about 45 miles
south of Montgomery. The concrete supplier had to bring a
portable concrete plant to the job, which required 25,000
cu yd of concrete.
 |
 |
|
Fast-track construction on a massive
scale precluded value engineering, but different options
were budgeted during the design process.
|
Power also was a problem. While
Alabama Power built a substation to service the plant, it
was not completed in time for the plant construction. Temporary
power was used until Alabama Power brought in a large portable
generator late in the job to help with equipment installation.
There also was no water at the site, which required the builder
to provide water trucks.
Site work also was a challenge.
The owner cleared the site and poured the building pad, but
several changes to the original layout required additional
civil design and construction. The site work included grading,
storm and sanitary sewers, potable and fire water lines, asphalt
and concrete paving and landscaping over the 50-acre site.
"When we got involved, the overall civil plan didnt
match with the size of the building," says Tynes.
While the owner added multiple
changes to the job and still wanted the schedule shortened,
Tynes says the project is the best he has worked on. "With
all of the challenges, we had good results," he says.
"The project came in on time and on budget."
(All photos courtesy of
Brice Building Co, ©2005 M. Lewis Kennedy, Jr.)
|