New Planning Method Can Deliver
Better Design-Build Projects Faster
By Sherif Fouad Hashem,
Consulting Engineering Group
 |
 |
|
Hashem
|
Recent surveys reveal
that design-build project delivery continues to grow in popularity
as it overpowers other traditional methods. Research has revealed
that, among other advantages, shortening project duration
is one main reason why owners select design-build. But for
design-build to maintain its current success, the collaborative
system has to live up to owners expectations and continue
to surprise the world with its ability to deliver projects
with unbeatable speed.
An investigation of how planners
at major design-build firms accelerate schedules yielded surprising
and to some extent disappointing findings. While the planners
realized the importance of overlapping design and construction
activities and attempted to achieve it, very few of them followed
a systematic, scientific method. The vast majority depend
only on their own judgment and experience and input from other
team members. This lack of a scientific basis for design and
construction overlap led in many cases to costly and time-consuming
rework and sometimes to significant schedule overruns.
Overlapping is good, but the question
is how to best achieve it. Too much overlapping of design
and construction can cause work to stop until the design catches
up, or even worse, to demolition of completed work. But an
insufficient amount undermines the benefits of design-build.
Fast-track design-build project planners need a system supported
by academia.
One answer may be my SAFEDB Methodology,
which establishes a scientific basis to the overlapping process.
SAFEDB is an abbreviation for A Sound Approach to Formulate
and Evaluate planning for large civil engineering fast-track
Design-Build projects. The core philosophy is that in-depth
knowledge of the nature and characteristics of each major
project component is the key to success. Planning therefore
has to follow scientifically based means and methods and must
be proactive.
In SAFEDB, the planning process
should start with the up-front selection of design solutions
and include the adoption of the construction means, methods
and techniques. The project plan therefore needs to be developed
by a planning team of senior design, construction and scheduling
professionals from within the design-build entity, rather
than just by senior planners with input from design and construction
professionals, as is common. By doing so, there is greater
intensity, knowledge and thought poured into the schedule
earlier in the process and a greater commitment to implement
the schedule when the project is under way.
Setting Goals
SAFEDB has three basic planning goals: 1) to ensure that
the selected design and construction solutions are the best
to serve their intended purposes; 2) to foresee probable problems
(failed tests, etc.) and to accommodate them into the schedule;
and 3) to compress the schedule by the maximum safe, practicable
application of overlapping activities.
These goals are accomplished by
following three basic methodology components: 1) axiomatic
design, 2) Graphical Evaluation and Review Technique (GERT),
and 3) concurrent engineering.
Axiomatic design theory primarily
is concerned with determining whether a design or construction
solution is good or bad. It divides the design-build process
into three main areas, or domainsfunctional requirements,
design parameters and construction variables. Predecessor
domains describe "what needs to be achieved", while
successors describe "how it can be done."
The process starts by specifying
the general functional requirements of the project in the
functional domain. Then, the design domain responds with several
design options, which then are measured against the functional
requirements for the best fit. After the best design option
is selected, the next level of functional requirements is
laid out and the cycle continues until design is finalized.
The same process is applied to
construction by zigzagging back and forth between design parameters
and construction variables until construction also is finalized.
The GERT method is a further development
of widely used Program Evaluation and Review Technique (PERT)a
network model developed in the 1950s that allows for randomness
in activity completion times. GERT, developed in the 1960s,
can handle more complex modeling situations. It explicitly
defines the rework loops and branches for different outcomes
in the project schedule and allows project planners to assign
probabilities to their occurrence. Probabilities are estimated
on the basis of historical statistics and experience with
similar circumstances.
The GERT approach can accommodate
the different scenarios that project activ-ities might encounter
so that the project planners can decide the final resource
allocation and/or countermeasure techniques.
Having selected the best design
and construction solutions and accounted for potential branching
and looping in SAFEDB steps one and two, applying the concurrent
engineering theory is a decisive step toward optimizing the
schedule by overlapping upstream design activities and pertinent
downstream construction.
The process starts with establishing
the fast-tracking characteristics of the various overlapped
design and construction activities. That is basically defined
in terms of the upstream activity evolution (UAE) and the
downstream activity sensitivity (DAS). UAE is the rate of
progress in the development of the upstream design activity,
while DAS describes how sensitive the downstream construction
activity is to changes in information transferred from the
upstream design activity.
In general, there are four basic
modes of combination between UAEs and DASs: Slow UAE with
Low DAS, Fast UAE with Low DAS, Slow UAE with High DAS and
Fast UAE with High DAS.
The SAFEDB methodology has established
that overlapping of activities should be carried out only
after careful consideration of the pre-defined activitys
fast-tracking characteristics. The table below summarizes
the outcome of the portion of the SAFEDB methodology looking
into overlapping. It provides a recommended generic numerical
overlapping strategy comprising all possible combinations
of upstream and downstream activity fast-tracking characteristics.
The values shown indicate the percentage of the upstream design
activity duration at which downstream construction activity
may start, in a start-to-start mode. Percentages of actual
completion of the upstream design activities likely to have
been accomplished at the time the downstream construction
activity starts also are given in red.
Click here to view pdf chart
Reliability of the information
developed in the upstream design activity has a major effect
on the extent of the safe overlapping of the same with the
downstream construction activity. In a design-build environment
with a reliable upstream design activity, the work produced
can be readily passed along to initiate the downstream construction
activity, resulting in a speedier design-build process.
One example would be the foundation
design for a multi-story building. Column loads can be calculated
first, once the structural model is established and decisive
load combinations are examined. Foundation design then can
be finalized and released for construction while design of
other structural elements (columns, slabs, beams) proceeds
in parallel.
On the other hand, if the upstream
design activity is highly unreliable, overlapping should be
avoided to minimize the possibility of reworking in the downstream.
An example of this would be hydraulic design of a closed-loop
pressurized water system. Hydraulic design should be fully
finalized after examining the various potential pumping and
shut-down scenarios before releasing any part of the network
for construction.
Sensitivity of the downstream construction
activity to changes or errors in the information transferred
from the upstream design activity also has a similar effect
on the amount of overlapping. For certain scenarios in which
a highly unreliable upstream design activity is followed by
a highly sensitive downstream activity, a schedule buffer,
such as a finish-to-start lag, is recommended. In this overlapping
strategy, the maximum amount of time allowed for upstream
activity completion is set at up to 160%. By doing so, planners
will have enough time to discover potential errors in the
upstream design activity and fix them, thereby avoiding any
costly impact of these errors on the downstream construction
activity.
For the most effective implementation of the SAFEDB methodology,
planners and project managers should focus on major activities
lying on the projects critical path. This should be
done until they move the project off that critical path and
onto a new critical path as overlapping continues. The process
continues until no further overlapping is practical or feasible.
Tools Needed
Unfortunately, the current state-of-art of the commercial
computer-aided planning programs do not yet support the SAFEDB
methodology and it can only be applied manually at this stage.
This could be an exhaustive task if applied to many parts
of a project. Further development of the currently available
project planning computer programs and software (such as Primavera
P3) to accommodate design-build needs to be based on SAFEDB
principles and could be a major advancement of design-build
projects. That could be done by expanding the scope of activity
definition to include fast-tracking parameters and to account
for looping and rework cycles in a probabilistic fashion.
Sherif Fouad Hashem is head of
the project management department,
Consulting Engineering Group, Doha, Qatar. He can be reached
at sheriffh@link.net or cell phone 974-581-7030.
|